1556 N LABAIG AVE 90028
Certificate Information: 1556 N LABAIG AVE 90028
- Application / Permit
- 19016-20000-39454
- Plan Check / Job No.
- B19VN21415
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR ALTERATION to (E) Single-family Dwelling to relocate closets, bathroom, kitchen, and to create a new full bathroom. EXTERIOR ALTERATION to remove windows, and to add five new windows.
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 11/1/2020
Permit Application Status History
| Submitted | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2019 | LUIS RINCON |
| Corrections Issued | 12/10/2019 | LUIS RINCON |
| Plan Check Approved | 1/24/2020 | SELLA BENYAMIN |
| Issued | 1/27/2020 | LADBS |
| Permit Finaled | 10/30/2020 | BRIAN SULLIVAN |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 12/13/2019 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 12/13/2019 | LAMBERT GIESSINGER |
| Tenant Habitability Plan | Cleared | 12/16/2019 | MICHAEL GREGERSON |
| "Q" conditions | Cleared | 1/23/2020 | VINCENT QUITORIANO |
| ZI | Cleared | 1/23/2020 | GISELLE CORELLA |
| ZI | Cleared | 1/23/2020 | VINCENT QUITORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/11/2020 | Conditional Approval | ROBERT CORNELL |
| Footing/Foundation/Slab | 2/14/2020 | Not Ready for Inspection | ROBERT CORNELL |
| Footing/Foundation/Slab | 3/5/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 3/11/2020 | Approved | ROBERT CORNELL |
| Deputy Drilled-In Anchors | 3/24/2020 | Conditional Approval | ROBERT CORNELL |
| ELECTRICAL-Rough | 4/14/2020 | Approved | BRIAN SULLIVAN |
| Shower Pan | 4/14/2020 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 4/14/2020 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/28/2020 | Corrections Issued | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/12/2020 | Partial Approval | BRIAN SULLIVAN |
| HVAC-Rough | 5/21/2020 | Approved | RAUL BARAJAS |
| Sewer | 5/27/2020 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/2/2020 | Approved | BRIAN SULLIVAN |
| Insulation | 6/2/2020 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 6/2/2020 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 6/8/2020 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 6/15/2020 | Approved | BRIAN SULLIVAN |
| Final | 10/30/2020 | Permit Finaled | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/30/2020 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 10/30/2020 | Approved | BRIAN SULLIVAN |