1093 S GAYLEY AVE 90024
Certificate Information: 1093 S GAYLEY AVE 90024
- Application / Permit
- 19016-20000-39319
- Plan Check / Job No.
- B19VN21362
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Barber Shop
- Work Description
- TENANT IMPROVEMENT - NON-STRUCTURAL REMODEL REMOVE TO REPLACE SKYLIGHTS (SAME SIZE/TYPE/LOCATION) AND REPLACE DRYWALL IN INTERIOR TENANT SPACE. NO CHANGE OF USE.
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/27/2022
Permit Application Status History
| Submitted | 12/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2019 | JENNIFER LEE |
| Corrections Issued | 12/9/2019 | JENNIFER LEE |
| Plan Check Approved | 1/3/2020 | SERGIO MUNIZ |
| Issued | 1/3/2020 | LADBS |
| Permit Finaled | 6/24/2022 | PAUL DAVIDSON |
Permit Application Clearance Information
| "D" conditions | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| Address approval | Cleared | 12/16/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2019 | APEKSHYA BAJRACHARYA |
| Miscellaneous | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| Specific Plan | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 12/16/2019 | HERMINIGILDO AGUSTIN |
| Specific Plan | Cleared | 1/3/2020 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | M S B Disaster Recovery Services Inc; Lic. No.: 858509-B | 30665 OLD HWY 395 ESCONDIDO, CA 92026 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/24/2020 | Approved | GRANT WOODS |
| Insulation | 10/18/2021 | Approved | PAUL DAVIDSON |
| Wood Frame | 10/18/2021 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 11/19/2021 | Partial Approval | PAUL DAVIDSON |
| METHANE-Final | 2/10/2022 | Approved | PAUL DAVIDSON |
| Final | 3/3/2022 | Corrections Issued | PAUL DAVIDSON |
| Smoke Detectors | 3/3/2022 | Approved | PAUL DAVIDSON |
| Final | 6/21/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Final | 6/24/2022 | Permit Finaled | PAUL DAVIDSON |