12131 W HUSTON ST 91607
Certificate Information: 12131 W HUSTON ST 91607
- Application / Permit
- 19016-20000-39193
- Plan Check / Job No.
- B19VN21300
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO (N) ACCESSORY DWELLING UNIT, PER AB 494 AND SB 229. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2019 | ALYSSA N NARCISO |
| Corrections Issued | 12/9/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 12/17/2019 | ROSENDO MEDINA |
| Plan Check Approved | 7/8/2020 | JEROME MAGAT PALMA |
| Issued | 7/27/2020 | APPLICANT |
| CofO in Progress | 3/23/2021 | BRENDAN LOONEY |
| Permit Finaled | 7/16/2021 | DANIEL ORRANTE |
| CofO Issued | 7/16/2021 | DANIEL ORRANTE |
| Permit Finaled | 7/16/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2019 | JEANIE LAM |
| Sewer availability | Cleared | 12/12/2019 | JEANIE LAM |
| Specific Plan | Cleared | 12/17/2019 | DANIEL SKOLNICK |
| Construction near power lines | Cleared | 6/18/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/18/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/16/2020 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/22/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Inspection | 9/22/2020 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/1/2020 | Partial Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 10/15/2020 | Conditional Approval | BRENDAN LOONEY |
| Gas Test | 10/15/2020 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 10/15/2020 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/30/2020 | Approved | THOMAS FINNILA |
| Wood Frame | 10/30/2020 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/10/2020 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 11/10/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Underground Mechanical | 11/10/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Underground Mechanical | 11/20/2020 | Partial Inspection | BRENDAN LOONEY |
| Wood Frame | 11/30/2020 | Partial Approval | DANIEL ORRANTE |
| Underground Mechanical | 12/9/2020 | Approved | BRENDAN LOONEY |
| Wood Frame | 12/9/2020 | Approved | BRENDAN LOONEY |
| Insulation | 12/22/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 1/6/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 1/6/2021 | Approved | BRENDAN LOONEY |
| Underground Mechanical | 1/6/2021 | Approved | BRENDAN LOONEY |
| Shower Pan | 1/13/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 1/25/2021 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 1/25/2021 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 1/25/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/8/2021 | Approved | ARAM AVEDISIAN |
| Final | 3/8/2021 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 3/8/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/8/2021 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 3/8/2021 | Approved | ARAM AVEDISIAN |
| Final | 3/19/2021 | OK to Issue CofO | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 3/19/2021 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 3/19/2021 | Approved | BRENDAN LOONEY |