135 S AVENUE 53 90042

Certificate Information: 135 S AVENUE 53 90042

Application / Permit
19016-20000-38892
Plan Check / Job No.
B19VN21109
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1ST & 2ND FLR INTERIOR REMODEL PER PLAN. (NO EXTERIOR ALTERATIONS)
Permit Issued
Issued on 1/3/2020
Issuing Office
Valley
Current Status
Permit Finaled on 7/31/2020

Permit Application Status History

Submitted 12/5/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 HAYATO TSUCHIYA
Corrections Issued 12/6/2019 HAYATO TSUCHIYA
Building Plans Picked Up 12/9/2019 APPLICANT
Plan Check Approved 12/23/2019 HAYATO TSUCHIYA
Issued 1/3/2020 LADBS
Permit Finaled 7/30/2020 HAMIK HARTOUNIAN

Permit Application Clearance Information

HPOZ Cleared 12/10/2019 KATIE DEBIASE
ZI Cleared 12/10/2019 KATIE DEBIASE
Eng Process Fee Ord 176,300 Cleared 12/16/2019 EMIL KYUPELYAN
Grading Pre-Inspection Cleared 12/16/2019 KIRK LINKLATER
Sewer availability Cleared 12/16/2019 EMIL KYUPELYAN

Contact Information

Architect Chun,, Youngmin; Lic. No.: C32890 1828 LINCOLN BLVD #B      SANTA MONICA, CA 90404
Contractor S M X Development; Lic. No.: 1027521-B 3579 E FOOTHILL BLVD #280      PASADENA, CA 91107
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/14/2020 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 1/16/2020 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 1/17/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 1/31/2020 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 2/10/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 2/21/2020 Corrections Issued ENRIQUE MIRELES
HVAC-Rough 2/21/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 2/21/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 2/26/2020 Approved ENRIQUE MIRELES
Wood Frame 3/2/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 3/6/2020 Approved ENRIQUE MIRELES
Insulation 3/17/2020 Not Ready for Inspection ENRIQUE MIRELES
Insulation 3/23/2020 Approved THOMAS LOGRASSO
Drywall Nailing 4/6/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 4/6/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/27/2020 Partial Approval CHRISTOPHER DELLEFIELD
Final 6/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 6/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/16/2020 SGSOV Approved HAMIK HARTOUNIAN
Final 7/2/2020 Corrections Issued HAMIK HARTOUNIAN
Smoke Detectors 7/2/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Final 7/21/2020 Corrections Issued ENRIQUE MIRELES
Smoke Detectors 7/21/2020 Approved ENRIQUE MIRELES
Pre-Inspection 7/24/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 7/30/2020 Permit Finaled HAMIK HARTOUNIAN