3748 N DOVER PL 90039
Certificate Information: 3748 N DOVER PL 90039
- Application / Permit
- 19016-20000-38887
- Plan Check / Job No.
- B19VN21101
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/27/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2019 | ALDOUS CHIC |
| Corrections Issued | 12/20/2019 | ALDOUS CHIC |
| Plan Check Approved | 12/31/2019 | HERNAN ARREOLA |
| Issued | 2/4/2020 | LADBS |
| CofO in Progress | 9/8/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/27/2020 | DEROLD HAUFF |
| CofO Issued | 9/27/2020 | DEROLD HAUFF |
| Permit Finaled | 9/27/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/20/2019 | LEE GUILBEAUX |
Contact Information
| Contractor | Mullins L Construction Inc; Lic. No.: 914806-B | P O BOX 7079 WOODLAND HILLS, CA 91365 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/19/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/9/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/20/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/1/2020 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/1/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/8/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/18/2020 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 5/18/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/29/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/15/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 6/22/2020 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 6/22/2020 | Approved | HAMIK HARTOUNIAN |
| Sewer | 8/4/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/4/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 9/4/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 9/4/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 9/4/2020 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/4/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/4/2020 | Approved | HAMIK HARTOUNIAN |