1462 S ROBERTSON BLVD 90035
Certificate Information: 1462 S ROBERTSON BLVD 90035
- Application / Permit
- 19016-20000-38635
- Plan Check / Job No.
- B19VN20980
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Dental Clinic
- Work Description
- CONVERT 12' x 70'-3" PORTION OF RETAIL TO DENTIST OFFICE
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- CofO Issued on 6/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | SELLA BENYAMIN |
| Corrections Issued | 12/17/2019 | SELLA BENYAMIN |
| Disabled Access Plans Picked Up | 12/18/2019 | APPLICANT |
| Quality Review Completed | 12/19/2019 | STEVEN KIM |
| Building Plans Picked Up | 12/23/2019 | APPLICANT |
| Plan Check Approved | 3/4/2020 | SELLA BENYAMIN |
| Issued | 1/7/2021 | APPLICANT |
| CofO in Progress | 5/12/2022 | JEFF BYTHEWAY |
| Permit Finaled | 6/10/2022 | DAVID TSAU |
| CofO Issued | 6/10/2022 | DAVID TSAU |
| Permit Finaled | 6/10/2022 | DAVID TSAU |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 2/26/2020 | VINCENT QUITORIANO |
| DAS Clearance | Cleared | 2/26/2020 | SELLA BENYAMIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/28/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: C24587 | 21243 VENTURA BLVD #115 WOODLAND HILLS, CA 91364 |
| Contractor | Safarian Construction Inc; Lic. No.: 861469-B | 20245 VIA MADRIGAL PORTER RANCH, CA 91326 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/23/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Drywall Nailing | 4/29/2021 | Corrections Issued | SORIN CIRSTOIU |
| Drywall Nailing | 5/18/2021 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 12/29/2021 | Conditional Approval | PAUL DAVIDSON |
| METHANE-Rough | 12/29/2021 | Approved | PAUL DAVIDSON |
| Wood Frame | 12/29/2021 | Conditional Approval | PAUL DAVIDSON |
| Drywall Nailing | 1/10/2022 | Approved | DERRICK SPENCER |
| T-Bar Ceiling | 1/11/2022 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/23/2022 | Partial Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 2/23/2022 | Approved | PAUL DAVIDSON |
| Footing/Foundation/Slab | 2/25/2022 | Approved | PAUL DAVIDSON |
| Final | 4/5/2022 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 4/5/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 4/5/2022 | Approved | GRANT WOODS |
| Wood Frame | 4/5/2022 | Approved | GRANT WOODS |
| Final | 5/5/2022 | Corrections Issued | JEFF BYTHEWAY |
| Final | 5/11/2022 | OK to Issue CofO | JEFF BYTHEWAY |