7325 1/2 N NEWCASTLE AVE 91335
Certificate Information: 7325 1/2 N NEWCASTLE AVE 91335
- Application / Permit
- 19016-20000-38579
- Plan Check / Job No.
- B19VN20923
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/15/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/2/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2019 | ANGELICA DAVE |
| Corrections Issued | 12/3/2019 | ANGELICA DAVE |
| Plan Check Approved | 1/15/2020 | ROSENDO MEDINA |
| Issued | 1/15/2020 | LADBS |
| CofO in Progress | 6/5/2020 | VINCENT HANLEY |
| Permit Finaled | 7/2/2020 | DONALD SUNSERI |
| CofO Issued | 7/2/2020 | DONALD SUNSERI |
| Permit Finaled | 7/2/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/3/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Hudson Partners Construction Llc; Lic. No.: 1045535-B | 11846 VENTURA BLVD STE 140 STUDIO CITY, CA 91604 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2020 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 2/21/2020 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/21/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 2/21/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/12/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 3/12/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/12/2020 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/12/2020 | SGSOV Not Ready | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/17/2020 | Corrections Issued | VINCENT HANLEY |
| Insulation | 3/17/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/25/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/25/2020 | Approved | VINCENT HANLEY |
| Insulation | 3/25/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/25/2020 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 3/31/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/31/2020 | Approved | VINCENT HANLEY |
| Final | 5/22/2020 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 5/22/2020 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/22/2020 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 5/22/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/5/2020 | Approved | VINCENT HANLEY |
| Final | 6/5/2020 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 6/5/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/5/2020 | Approved | VINCENT HANLEY |