7276 N HATILLO AVE 91306

Certificate Information: 7276 N HATILLO AVE 91306

Application / Permit
19016-20000-38483
Plan Check / Job No.
B19VN20865
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 1/29/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2019 APPLICANT
Assigned to Plan Check Engineer 12/2/2019 JEFFREY TANGONAN
Corrections Issued 12/2/2019 JEFFREY TANGONAN
Building Plans Picked Up 12/5/2019 APPLICANT
Plan Check Approved 1/22/2020 JEFFREY TANGONAN
Issued 1/29/2020 LADBS
CofO in Progress 4/3/2020 HENRY KIM
Permit Finaled 4/20/2020 DONALD SUNSERI
CofO Issued 4/20/2020 DONALD SUNSERI
Permit Finaled 4/20/2020 DONALD SUNSERI

Permit Application Clearance Information

Construction within easement Cleared 1/16/2020 RIDWAN HARDY
Address approval Cleared 1/17/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 1/17/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 1/17/2020 MARKOS PEREZ-BRAN

Contact Information

Contractor Pearl Remodeling; Lic. No.: 955824-B 6803 YARMOUTH AVENUE      RESEDA, CA 91335

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/6/2020 Approved HENRY KIM
Pre-Inspection 2/6/2020 Corrections Issued HENRY KIM
Sewer 2/6/2020 Approved HENRY KIM
Underground Mechanical 2/6/2020 Partial Approval HENRY KIM
PLUMBING-Rough 2/13/2020 Partial Approval HENRY KIM
Rough-Elec/Plmb/HVAC 2/19/2020 Approved HENRY KIM
Wood Frame 2/19/2020 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 2/24/2020 Approved HENRY KIM
Green Building Rough 2/24/2020 Approved HENRY KIM
HVAC-Rough 2/24/2020 Approved HENRY KIM
Insulation 2/24/2020 Approved HENRY KIM
Interior/Exterior Lathing 2/24/2020 Approved HENRY KIM
Drywall Nailing 2/26/2020 Approved HENRY KIM
ELECTRICAL-Final 3/25/2020 Corrections Issued HENRY KIM
Final 3/25/2020 Corrections Issued HENRY KIM
Gas Test 3/25/2020 Approved HENRY KIM
Green Building Final 3/25/2020 Approved HENRY KIM
HVAC-Final 3/25/2020 Corrections Issued HENRY KIM
PLUMBING-Final 3/25/2020 Corrections Issued HENRY KIM
Smoke Detectors 3/25/2020 Approved HENRY KIM
Underground Mechanical 3/25/2020 Approved HENRY KIM
ELECTRICAL-Final 4/3/2020 Approved HENRY KIM
Final 4/3/2020 OK to Issue CofO HENRY KIM
HVAC-Final 4/3/2020 Approved HENRY KIM
PLUMBING-Final 4/3/2020 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 4/3/2020 SGSOV Approved HENRY KIM