925 W BURRELL ST 90292
Certificate Information: 925 W BURRELL ST 90292
- Application / Permit
- 19016-20000-38178
- Plan Check / Job No.
- B19VN20663
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' x 26' DET. STORAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). CONSTRUCTION DESIGN PER ENGR.
- Permit Issued
- Issued on 12/26/2024
- Issuing Office
- Current Status
- CofO Issued on 1/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2019 | PINANK PATEL |
| Corrections Issued | 12/2/2019 | PINANK PATEL |
| Applicant returned to address corrections | 12/11/2019 | PINANK PATEL |
| Applicant returned to address corrections | 6/16/2021 | PINANK PATEL |
| Building Plans Picked Up | 8/13/2021 | APPLICANT |
| Plan Check Approved | 12/24/2024 | ANGELICA MARTINEZ |
| Issued | 12/26/2024 | APPLICANT |
| Permit Finaled | 1/15/2026 | CLAUDIO MORENO |
| CofO Issued | 1/15/2026 | CLAUDIO MORENO |
| Permit Finaled | 1/15/2026 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | JOHN LIN |
| Sewer availability | Cleared | 12/3/2019 | JOHN LIN |
| Miscellaneous | Cleared | 9/24/2020 | ANACANY HURTADO |
| Specific Plan | Cleared | 9/21/2021 | VALERIA CEJA |
| Specific Plan | Cleared | 9/21/2021 | VALERIA CEJA |
| Coastal Zone | Cleared | 12/6/2024 | ASHLEY RODARTE |
| Specific Plan | Cleared | 12/6/2024 | ASHLEY RODARTE |
| Specific Plan | Cleared | 12/6/2024 | ASHLEY RODARTE |
| ZI | Cleared | 12/6/2024 | ASHLEY RODARTE |
| ZI | Cleared | 12/6/2024 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/1/2025 | No Access for Inspection | RYAN BARNES |
| Pre-Inspection | 7/31/2025 | Partial Approval | RYAN BARNES |
| Footing/Foundation/Slab | 9/17/2025 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 10/6/2025 | Approved | RYAN BARNES |
| Green Building Rough | 10/6/2025 | Approved | RYAN BARNES |
| HVAC-Rough | 10/6/2025 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 10/6/2025 | Partial Approval | RYAN BARNES |
| METHANE-Rough | 10/6/2025 | Approved | RYAN BARNES |
| ELECTRICAL-Rough | 10/15/2025 | Approved | RYAN BARNES |
| Insulation | 10/15/2025 | Approved | RYAN BARNES |
| PLUMBING-Rough | 10/15/2025 | Approved | RYAN BARNES |
| Drywall Nailing | 11/5/2025 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 11/5/2025 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 12/19/2025 | Approved | RYAN BARNES |
| Final | 12/19/2025 | Conditional Approval | RYAN BARNES |
| Green Building Final | 12/19/2025 | Approved | RYAN BARNES |
| PLUMBING-Final | 12/19/2025 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 12/19/2025 | Approved | RYAN BARNES |