6864-6866 N SYLVIA AVE 91335

Certificate Information: 6864-6866 N SYLVIA AVE 91335

Application / Permit
19016-20000-38159
Plan Check / Job No.
B19VN20637
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC WALK IN: CONVERT THE 20'-2"X 20'-4"(E) ATTACHED TWO CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT, PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 1/22/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 YAQUB MIRZA
Corrections Issued 11/26/2019 YAQUB MIRZA
Plan Check Approved 1/13/2020 PARISA ZAHABI
Issued 1/22/2020 LADBS
CofO in Progress 5/10/2020 VINCENT HANLEY
CofO Issued 6/16/2020 DONALD SUNSERI
Permit Finaled 6/16/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 11/26/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/26/2019 GUILLERMO PETRA
Sewer availability Cleared 11/26/2019 GUILLERMO PETRA
Construction near power lines Cleared 1/4/2020 RIDWAN HARDY

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B 20501 VENTURA BLVD #135      WOODLAND HILLS, CA 91364

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2020 Approved VINCENT HANLEY
PLUMBING-Rough 2/7/2020 Partial Approval VINCENT HANLEY
Sewer 2/7/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 2/13/2020 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 2/13/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/13/2020 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 2/14/2020 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 2/14/2020 Approved VINCENT HANLEY
HVAC-Rough 2/14/2020 Approved VINCENT HANLEY
PLUMBING-Rough 2/14/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/20/2020 Partial Approval VINCENT HANLEY
Green Building Rough 2/20/2020 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 2/25/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/25/2020 Approved VINCENT HANLEY
Insulation 2/25/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/25/2020 Partial Approval VINCENT HANLEY
Rough-Elec/Plmb/HVAC 2/25/2020 Approved VINCENT HANLEY
Drywall Nailing 2/27/2020 Corrections Issued VINCENT HANLEY
Drywall Nailing 3/3/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/5/2020 Corrections Issued VINCENT HANLEY
Interior/Exterior Lathing 3/11/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 5/8/2020 Approved VINCENT HANLEY
ELECTRICAL-Final 5/8/2020 Approved VINCENT HANLEY
Final 5/8/2020 OK to Issue CofO VINCENT HANLEY
Green Building Final 5/8/2020 Approved VINCENT HANLEY
Green Building Rough 5/8/2020 Approved VINCENT HANLEY
HVAC-Final 5/8/2020 Approved VINCENT HANLEY
PLUMBING-Final 5/8/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/8/2020 SGSOV Approved VINCENT HANLEY
Smoke Detectors 5/8/2020 Approved VINCENT HANLEY