6864-6866 N SYLVIA AVE 91335
Certificate Information: 6864-6866 N SYLVIA AVE 91335
- Application / Permit
- 19016-20000-38159
- Plan Check / Job No.
- B19VN20637
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ECPC WALK IN: CONVERT THE 20'-2"X 20'-4"(E) ATTACHED TWO CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT, PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/22/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/16/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | YAQUB MIRZA |
| Corrections Issued | 11/26/2019 | YAQUB MIRZA |
| Plan Check Approved | 1/13/2020 | PARISA ZAHABI |
| Issued | 1/22/2020 | LADBS |
| CofO in Progress | 5/10/2020 | VINCENT HANLEY |
| CofO Issued | 6/16/2020 | DONALD SUNSERI |
| Permit Finaled | 6/16/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Address approval | Cleared | 11/26/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 11/26/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 1/4/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/7/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/7/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 2/7/2020 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/13/2020 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 2/13/2020 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 2/13/2020 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/14/2020 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/14/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/14/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/14/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/20/2020 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 2/20/2020 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/25/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2020 | Approved | VINCENT HANLEY |
| Insulation | 2/25/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/25/2020 | Partial Approval | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 2/25/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/27/2020 | Corrections Issued | VINCENT HANLEY |
| Drywall Nailing | 3/3/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/5/2020 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/11/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/8/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/8/2020 | Approved | VINCENT HANLEY |
| Final | 5/8/2020 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 5/8/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/8/2020 | Approved | VINCENT HANLEY |
| HVAC-Final | 5/8/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/8/2020 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/8/2020 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 5/8/2020 | Approved | VINCENT HANLEY |