2822 S REDONDO BLVD 90016
Certificate Information: 2822 S REDONDO BLVD 90016
- Application / Permit
- 19016-20000-37978
- Plan Check / Job No.
- B19VN20556
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO THE (E) SFD, RELOCATE THE (E) KITCHEN, AND CREATE A BATHROOM. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 7/6/2020
- Issuing Office
- Current Status
- Permit Finaled on 12/23/2021
Permit Application Status History
| Submitted | 11/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2019 | ARTIN ZARUKIAN |
| Plan Check Approved | 11/25/2019 | ARTIN ZARUKIAN |
| Issued | 7/6/2020 | APPLICANT |
| Permit Finaled | 12/22/2021 | JOSE AVILA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Nigosian,, Michael Nickolas; Lic. No.: C35308 | 75-572 PAINTED DESERT DRIVE INDIAN WELLS, CA 92210 |
| Contractor | 3.1 Construction; Lic. No.: 1018269-B | 14017 DUNROBIN AVE BELLFLOWER, CA 90706 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/14/2020 | Partial Inspection | DAVID CHAN |
| ELECTRICAL-Rough | 7/14/2020 | Partial Inspection | DAVID CHAN |
| PLUMBING-Rough | 7/14/2020 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 2/25/2021 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 4/5/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/5/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/12/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/12/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/23/2021 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/29/2021 | Not Ready for Inspection | BENEVA JACKSON |
| BUILDING-Rough-Frame | 7/6/2021 | Approved | STUART CHAPMAN |
| Insulation | 7/20/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 7/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 8/10/2021 | Partial Approval | DAVID FEILER |
| Insulation | 8/10/2021 | Approved | DAVID FEILER |
| Drywall Nailing | 8/19/2021 | Approved | CALEB MEISTER |
| Final | 11/30/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 11/30/2021 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 11/30/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 12/8/2021 | Approved | JOSE AVILA |
| Smoke Detectors | 12/8/2021 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/13/2021 | Approved | JOSE AVILA |
| HVAC-Final | 12/13/2021 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 12/16/2021 | Corrections Issued | JOSE AVILA |
| Final | 12/22/2021 | Permit Finaled | JOSE AVILA |