5227 N STROHM AVE 91601
Certificate Information: 5227 N STROHM AVE 91601
- Application / Permit
- 19016-20000-37679
- Plan Check / Job No.
- B19VN20391
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- RFRAME ROOF OF DETACHED GARAGE/STORAGE AND CONVERT INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 11/21/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | ALDOUS CHIC |
| Corrections Issued | 11/21/2019 | ALDOUS CHIC |
| Plan Check Approved | 11/21/2019 | HAYATO TSUCHIYA |
| Issued | 11/21/2019 | LADBS |
| CofO in Progress | 7/23/2021 | DANIEL DREW |
| CofO Issued | 9/14/2021 | MICHAEL SMITH |
| Permit Finaled | 9/14/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 11/21/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | 13302 FILMORE ST PACOIMA, CA 91331 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/10/2019 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 12/18/2019 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/13/2020 | Partial Approval | DANIEL DREW |
| ELECTRICAL-Rough | 11/25/2020 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/25/2020 | Corrections Issued | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 12/2/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 12/3/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 12/8/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 12/8/2020 | Approved | DANIEL DREW |
| Green Building Rough | 12/8/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 12/8/2020 | Approved | DANIEL DREW |
| Insulation | 12/15/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 12/18/2020 | Not Ready for Inspection | DANIEL DREW |
| Sewer | 12/18/2020 | Approved | DANIEL DREW |
| Underground Mechanical | 12/18/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 12/23/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 12/23/2020 | Approved | DANIEL DREW |
| Final | 4/1/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 4/1/2021 | Corrections Issued | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 4/1/2021 | SGSOV Not Ready | DANIEL DREW |
| Smoke Detectors | 4/1/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 4/16/2021 | Approved | DANIEL DREW |
| Service/Power Release | 4/16/2021 | Not Ready for Inspection | DANIEL DREW |
| Final | 5/4/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 5/4/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Not Ready | DANIEL DREW |
| Service/Power Release | 5/4/2021 | Not Ready for Inspection | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 5/14/2021 | SGSOV Approved | DANIEL DREW |
| Final | 7/22/2021 | OK to Issue CofO | DANIEL DREW |