312 S IRVING BLVD 90020
Certificate Information: 312 S IRVING BLVD 90020
- Application / Permit
- 19016-20000-37619
- Plan Check / Job No.
- B19VN20353
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE DETACHED GARAGE AND WASHROOM INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER DESIGN. "COMPLY WITH DEPARTMENT ORDER effective date 11/23/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". See comments.
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- CofO Issued on 7/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | ANGELICA DAVE |
| Corrections Issued | 11/21/2019 | ANGELICA DAVE |
| Applicant returned to address corrections | 7/22/2020 | THOMAS SHERMAN |
| Applicant returned to address corrections | 2/19/2021 | ANGELICA DAVE |
| Plan Check Approved | 10/26/2021 | ANGELICA MARTINEZ |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| Issued | 11/4/2021 | APPLICANT |
| CofO in Progress | 7/1/2022 | ZEYDI STEWART |
| CofO in Progress | 7/1/2022 | ZEYDI STEWART |
| CofO Issued | 7/20/2022 | DANIEL SANCHEZ |
| Permit Finaled | 7/20/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| HPOZ | Cleared | 10/14/2021 | LYDIA CHAPMAN |
| Address approval | Cleared | 10/21/2021 | WALLIE JONG |
| Sewer availability | Cleared | 10/21/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2021 | WALLIE JONG |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/15/2021 | Corrections Issued | ZEYDI STEWART |
| ELECTRICAL-Final | 12/3/2021 | Corrections Issued | ZEYDI STEWART |
| PLUMBING-Rough | 12/3/2021 | Corrections Issued | ZEYDI STEWART |
| Smoke Detectors | 12/3/2021 | Corrections Issued | ZEYDI STEWART |
| Special/Order Compliance | 12/3/2021 | Partial Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 2/9/2022 | Corrections Issued | PIERRE VEGA |
| ELECTRICAL-Final | 2/9/2022 | Corrections Issued | PIERRE VEGA |
| Final | 2/9/2022 | Corrections Issued | PIERRE VEGA |
| Green Building Final | 2/9/2022 | Not Ready for Inspection | PIERRE VEGA |
| Green Building Rough | 2/9/2022 | Not Ready for Inspection | PIERRE VEGA |
| HVAC-Final | 2/9/2022 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Final | 2/9/2022 | Corrections Issued | PIERRE VEGA |
| Rough-Elec/Plmb/HVAC | 2/9/2022 | Corrections Issued | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 2/9/2022 | SGSOV Not Ready | PIERRE VEGA |
| Smoke Detectors | 2/9/2022 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Final | 2/18/2022 | Not Ready for Inspection | PIERRE VEGA |
| Sewer | 2/18/2022 | Not Ready for Inspection | PIERRE VEGA |
| Drywall Nailing | 4/15/2022 | No Access for Inspection | PIERRE VEGA |
| ELECTRICAL-Final | 4/15/2022 | No Access for Inspection | PIERRE VEGA |
| Drywall Nailing | 4/22/2022 | Approved | ZEYDI STEWART |
| ELECTRICAL-Final | 4/22/2022 | Corrections Issued | ZEYDI STEWART |
| Special/Order Compliance | 4/22/2022 | Partial Inspection | PIERRE VEGA |
| Sewer | 4/27/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Drywall Nailing | 5/3/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Corrections Issued | ZEYDI STEWART |
| Sewer | 5/3/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Special/Order Compliance | 5/3/2022 | Partial Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 6/6/2022 | Approved | ZEYDI STEWART |
| Final | 6/6/2022 | Partial Inspection | ZEYDI STEWART |
| Green Building Final | 6/6/2022 | Approved | ZEYDI STEWART |
| Green Building Rough | 6/6/2022 | Approved | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Not Ready | ZEYDI STEWART |
| Smoke Detectors | 6/6/2022 | Approved | ZEYDI STEWART |
| Final | 7/1/2022 | OK to Issue CofO | ZEYDI STEWART |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Approved | ZEYDI STEWART |