145 N LA BREA AVE SUITE D 90036
Certificate Information: 145 N LA BREA AVE SUITE D 90036
- Application / Permit
- 19016-20000-37123
- Plan Check / Job No.
- B19VN20008
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Furniture Store
- Work Description
- CHANGE OF USE OF 102'11-1/4"X32'1-1/2" (3069 SF) ART GALLERY TO RETAIL FURNITURE. NO STRUCTURAL CHANGES.
- Permit Issued
- Issued on 1/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/4/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | MARVEL DELACRUZ |
| Corrections Issued | 11/30/2019 | MARVEL DELACRUZ |
| Quality Review Completed | 12/4/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 12/5/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 12/5/2019 | APPLICANT |
| Plan Check Approved | 1/8/2020 | MARVEL DELACRUZ |
| Issued | 1/9/2020 | LADBS |
| CofO in Progress | 2/4/2020 | WINSTON DUNNING |
| CofO Issued | 2/4/2020 | WINSTON DUNNING |
| Permit Finaled | 2/4/2020 | WINSTON DUNNING |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 12/18/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 12/18/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 12/18/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 12/18/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 12/18/2019 | HERMINIGILDO AGUSTIN |
| DAS Clearance | Cleared | 12/23/2019 | NORLITO MEDRANO |
| Comm Cor/Mini-Mall | Cleared | 1/2/2020 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2020 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 1/2/2020 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/10/2020 | Conditional Approval | EDWIN GREGORYONA |
| METHANE-Final | 1/10/2020 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 1/10/2020 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 1/10/2020 | Approved | EDWIN GREGORYONA |