13019 W VICTORY BLVD 91606

Certificate Information: 13019 W VICTORY BLVD 91606

Application / Permit
19016-20000-36821
Plan Check / Job No.
B19VN19817
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Clinic
Work Description
CHANGE OF USE FROM (E) 150' X 81'5" (11,883 SQ.FT. ) RETAIL TO DIALYSIS MEDICAL CLINIC WITH NON STRUCTURAL T.I. AND (N) 3-HR FIREWALL TO SEPARATE BUILDING AND UPGRADING CONSTRUCTION TO TYPE V-A CONSTRUCTION (OSHPD 3). NFPA 13 FIRE SPRINKLER THROUGHOUT THE BUILDING , ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/20/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 ALDOUS CHIC
Corrections Issued 12/2/2019 ALDOUS CHIC
Quality Review Completed 12/3/2019 ABDUL CHEGENI
Building Plans Picked Up 12/6/2019 APPLICANT
Disabled Access Plans Picked Up 12/6/2019 APPLICANT
Green Plans Picked Up 12/6/2019 APPLICANT
Applicant returned to address corrections 4/1/2020 ALDOUS CHIC
Applicant returned to address corrections 4/21/2020 RARES BODEA
Plan Check Approved 4/23/2020 RARES BODEA
Issued 5/20/2020 LADBS
CofO in Progress 7/30/2021 ROBERT DAVIS
Permit Finaled 8/10/2021 JEFFREY DURAN
CofO Issued 8/10/2021 JEFFREY DURAN
Permit Finaled 8/10/2021 JEFFREY DURAN

Permit Application Clearance Information

"D" conditions Cleared 12/9/2019 HERMINIGILDO AGUSTIN
"Q" conditions Cleared 12/9/2019 HERMINIGILDO AGUSTIN
"T" removal Cleared 12/9/2019 HERMINIGILDO AGUSTIN
CPC Cleared 12/9/2019 HERMINIGILDO AGUSTIN
Hydrant and Access approval Cleared 12/9/2019 GEORGE SUCHAND
ZA Case Cleared 12/9/2019 HERMINIGILDO AGUSTIN
Eng Process Fee Ord 176,300 Cleared 12/13/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/13/2019 EMIL KYUPELYAN
Address approval Cleared 1/27/2020 ADRIAN CASTRO
DAS Clearance Cleared 2/3/2020 NORLITO MEDRANO
Green Code Cleared 2/3/2020 MICHAEL AYERS
Fire Marshall Fire Life Safety Cleared 2/5/2020 VIDAL GARCIA

Contact Information

Architect Elliott,, Bert Michael; Lic. No.: C8623 16421 WIMBLEDON LANE      HUNTINGTON BEACH, CA 92649
Contractor Rote Brothers Constructors Inc; Lic. No.: 1008500-B 1383 E HILLCREST DRIVE      THOUSAND OAKS, CA 91362
Engineer Skudlarski,, Jason James; Lic. No.: C67712 9751 OLYMPIC DR      HUNTINGTON BEACH, CA 92646

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 5/22/2020 Not Ready for Inspection ROBERT DAVIS
Wood Frame 5/22/2020 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 5/27/2020 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 5/29/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 6/9/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 6/10/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 6/11/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 6/12/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 6/15/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 6/17/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 6/18/2020 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 6/18/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 6/19/2020 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 6/22/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 6/22/2020 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/22/2020 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 6/22/2020 Partial Approval ROBERT DAVIS
Deputy Fireproofing 6/23/2020 Conditional Approval ROBERT DAVIS
Green Building Rough 6/30/2020 Approved ROBERT DAVIS
Insulation 6/30/2020 Approved ROBERT DAVIS
Structural Steel Frame 6/30/2020 Approved ROBERT DAVIS
Deputy Drilled-In Anchors 7/29/2020 Conditional Approval ROBERT DAVIS
Footing/Foundation/Slab 7/30/2020 Partial Approval ROBERT DAVIS
Deputy Fireproofing 8/6/2020 Conditional Approval ROBERT DAVIS
Drywall Nailing 8/6/2020 Partial Approval ROBERT DAVIS
Deputy Fireproofing 8/7/2020 Approved HAMID PISHEHVAR
Deputy Fireproofing 8/10/2020 Conditional Approval ROBERT DAVIS
Drywall Nailing 8/20/2020 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 8/20/2020 Partial Approval ROBERT DAVIS
Drywall Nailing 8/25/2020 Partial Approval JOHN KITCKO
Insulation 8/26/2020 Partial Approval DANIEL VARNUM
Drywall Nailing 8/28/2020 Partial Approval ROBERT DAVIS
Drywall Nailing 9/1/2020 Partial Approval ROBERT DAVIS
Deputy Fireproofing 9/4/2020 Conditional Approval ROBERT DAVIS
Deputy Fireproofing 9/8/2020 Conditional Approval ROBERT DAVIS
Light Gage Steel Frame 9/14/2020 Approved ROBERT DAVIS
Drywall Nailing 9/16/2020 Partial Approval ROBERT DAVIS
Drywall Nailing 9/25/2020 Approved ROBERT DAVIS
T-Bar Ceiling 11/5/2020 Partial Approval ROBERT DAVIS
T-Bar Ceiling 11/17/2020 Approved ROBERT DAVIS
Interior/Exterior Lathing 11/20/2020 Partial Inspection ANDREW DORSO
Special/Order Compliance 3/12/2021 Approved ROBERT DAVIS
Final 7/22/2021 OK to Issue CofO ROBERT DAVIS
Green Building Final 7/22/2021 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 7/22/2021 SGSOV Approved ROBERT DAVIS
Smoke Detectors 7/22/2021 Approved ROBERT DAVIS
Wood Frame 7/22/2021 Approved ROBERT DAVIS