10651 N BALBOA BLVD 91344

Certificate Information: 10651 N BALBOA BLVD 91344

Application / Permit
19016-20000-36655
Plan Check / Job No.
B19VN19732
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
TENANT IMPROVEMENT TO (E) RESTARUANT W/ OUTDOOR DINING; RESTRIPE PORTION OF PARKING TO ADD ACCESSIBLE STALL PER ZA-2019-718-CU-DRB-SPP
Permit Issued
Issued on 12/2/2020
Issuing Office
Current Status
Permit Finaled on 4/22/2021

Permit Application Status History

Submitted 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 NILOOFAR MEHRAIN
Corrections Issued 11/25/2019 NILOOFAR MEHRAIN
Quality Review Completed 11/25/2019 GUANG MIN TUNG
Building Plans Picked Up 12/5/2019 APPLICANT
Disabled Access Plans Picked Up 12/5/2019 APPLICANT
Green Plans Picked Up 12/5/2019 APPLICANT
Applicant returned to address corrections 9/8/2020 NILOOFAR MEHRAIN
Plan Check Approved 10/13/2020 NILOOFAR MEHRAIN
Issued 12/2/2020 APPLICANT
Permit Finaled 4/21/2021 JEFFREY FULTON

Permit Application Clearance Information

Green Code Cleared 11/13/2019 MICHAEL AYERS
Miscellaneous Cleared 3/9/2020 PABLO ESTRADA
ZA Case Cleared 3/9/2020 PABLO ESTRADA
ZA Case Cleared 3/9/2020 PABLO ESTRADA
ZA Case Cleared 3/9/2020 PABLO ESTRADA
DAS Clearance Cleared 6/1/2020 NORLITO MEDRANO
"Q" conditions Cleared 8/10/2020 MIGUEL GAMBOA
Comm Cor/Mini-Mall Cleared 8/10/2020 MIGUEL GAMBOA
Specific Plan Cleared 8/10/2020 MIGUEL GAMBOA
ZI Cleared 8/10/2020 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 8/18/2020 LEE GUILBEAUX
Sewer availability Cleared 8/18/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/18/2020 LEE GUILBEAUX
Food establishment approval Cleared 9/8/2020 LACDHS APPROVED
Food Service Establishment Cleared 9/10/2020 PAWAN VERMA
Hydrant and Access approval Cleared 9/23/2020 MATTHEW CRAIG
ZA Case Cleared 9/28/2020 PABLO ESTRADA

Contact Information

Contractor Clockwork Construction Inc; Lic. No.: 1042273-B 5656 CORPORATE AVE STE 200      CYPRESS, CA 90630

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/1/2021 Corrections Issued JEFFREY FULTON
Footing/Foundation/Slab 2/8/2021 Approved JEFFREY FULTON
Pre-Inspection 2/22/2021 Not Ready for Inspection JEFFREY FULTON
Final 2/24/2021 Corrections Issued JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 2/24/2021 SGSOV Approved JEFFREY FULTON
Smoke Detectors 2/24/2021 Approved JEFFREY FULTON
Final 4/21/2021 Permit Finaled JEFFREY FULTON