5732 N CORTEEN PL 91607
Certificate Information: 5732 N CORTEEN PL 91607
- Application / Permit
- 19016-20000-36558
- Plan Check / Job No.
- B19VN19672
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (29'-0"x 24'-3") IRR SHAPE 2ND STORY & CONVERT (E) 2-CAR DET. GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. WORK PER ENGINEER..
- Permit Issued
- Issued on 6/17/2020
- Issuing Office
- Current Status
- CofO Issued on 7/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2019 | TROY DEGUZMAN |
| Corrections Issued | 11/13/2019 | TROY DEGUZMAN |
| Building Plans Picked Up | 11/14/2019 | APPLICANT |
| Plan Check Approved | 6/17/2020 | TROY DEGUZMAN |
| Issued | 6/17/2020 | APPLICANT |
| CofO in Progress | 6/7/2021 | RICHARD DOCKUS |
| Permit Finaled | 7/20/2021 | MICHAEL SMITH |
| CofO Issued | 7/20/2021 | MICHAEL SMITH |
| Permit Finaled | 7/20/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 6/2/2020 | DAVID MATSON |
| Address approval | Cleared | 6/16/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/16/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/16/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 6/17/2020 | JORGE MEJIA LEMUS |
Contact Information
| Architect | Henderson,, Aaron Harold; Lic. No.: C18373 | 1442 E. WOODBURY ROAD PASADENA, CA 91104 |
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/7/2020 | Approved | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 7/16/2020 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 7/23/2020 | Approved | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 8/3/2020 | Conditional Approval | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2020 | Approved | BRENDAN LOONEY |
| Green Building Rough | 8/20/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2020 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/9/2020 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/9/2020 | Conditional Approval | BRENDAN LOONEY |
| Green Building Rough | 10/9/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 10/9/2020 | Approved | BRENDAN LOONEY |
| Insulation | 12/21/2020 | Corrections Issued | BRENDAN LOONEY |
| Drywall Nailing | 12/29/2020 | Approved | BRENDAN LOONEY |
| Green Building Rough | 12/29/2020 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/29/2020 | Partial Inspection | BRENDAN LOONEY |
| Gas Test | 2/19/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Final | 2/19/2021 | Approved | BRENDAN LOONEY |
| Gas Test | 2/24/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 3/3/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 3/3/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 3/3/2021 | Approved | BRENDAN LOONEY |
| Green Building Final | 3/3/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 3/3/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Service/Power Release | 3/3/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Smoke Detectors | 3/3/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Final | 3/5/2021 | Approved | BRENDAN LOONEY |
| Final | 4/14/2021 | Partial Inspection | RICHARD DOCKUS |
| Green Building Final | 4/14/2021 | Conditional Approval | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/14/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 4/14/2021 | Approved | RICHARD DOCKUS |
| Final | 5/20/2021 | OK to Issue CofO | RICHARD DOCKUS |
| Green Building Final | 5/20/2021 | Approved | RICHARD DOCKUS |