8519 N NEWCASTLE AVE 91325

Certificate Information: 8519 N NEWCASTLE AVE 91325

Application / Permit
19016-20000-36497
Plan Check / Job No.
B19VN19633
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 30' X 25' GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 10/14/2020
Issuing Office
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 PARISA ZAHABI
Green Plans Picked Up 12/10/2019 APPLICANT
Corrections Issued 12/12/2019 PARISA ZAHABI
Quality Review Completed 12/17/2019 OMID HEDAYAT
Building Plans Picked Up 12/17/2019 APPLICANT
Applicant returned to address corrections 2/11/2020 PARISA ZAHABI
Applicant returned to address corrections 2/24/2020 PARISA ZAHABI
Plan Check Approved 9/4/2020 PARISA ZAHABI
Issued 10/14/2020 APPLICANT
CofO in Progress 8/4/2021 MATTHEW NELSON
Permit Finaled 12/17/2021 MICHAEL SMITH
CofO Issued 12/17/2021 MICHAEL SMITH
Permit Finaled 12/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/27/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/27/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/27/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 1/27/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 2/6/2020 AARON COSTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/10/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 11/10/2020 Partial Approval MARK JOHNSON
Pre-Inspection 11/10/2020 Approved MARK JOHNSON
Footing/Foundation/Slab 11/17/2020 Approved MARK JOHNSON
ELECTRICAL-Rough 12/21/2020 Approved MARK JOHNSON
Sewer 12/21/2020 Corrections Issued MARK JOHNSON
Gas Test 12/29/2020 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 12/29/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 12/29/2020 Not Ready for Inspection MARK JOHNSON
Sewer 12/29/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 1/11/2021 Corrections Issued MARK JOHNSON
Gas Test 1/11/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 1/11/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 1/11/2021 Approved MARK JOHNSON
PLUMBING-Rough 1/11/2021 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 1/19/2021 Partial Approval DAVID MATSON
Gas Test 1/19/2021 Partial Approval DAVID MATSON
Green Building Rough 1/19/2021 Approved DAVID MATSON
HVAC-Rough 1/19/2021 Partial Approval DAVID MATSON
PLUMBING-Rough 1/19/2021 Approved DAVID MATSON
Underground Mechanical 1/19/2021 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 1/28/2021 Approved MARK JOHNSON
Gas Test 1/28/2021 Partial Approval MARK JOHNSON
PLUMBING-Rough 1/28/2021 Approved MARK JOHNSON
Underground Mechanical 1/28/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 2/2/2021 Not Ready for Inspection MARK JOHNSON
Interior/Exterior Lathing 2/5/2021 Approved MARK JOHNSON
Insulation 2/16/2021 Approved MARK JOHNSON
Drywall Nailing 3/1/2021 Approved MARK JOHNSON
ELECTRICAL-Final 4/23/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Final 4/23/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Final 8/4/2021 Approved MATTHEW NELSON
Final 8/4/2021 OK to Issue CofO MATTHEW NELSON
Green Building Final 8/4/2021 Approved MATTHEW NELSON
HVAC-Final 8/4/2021 Approved MATTHEW NELSON
PLUMBING-Final 8/4/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Approved MATTHEW NELSON
Smoke Detectors 8/4/2021 Approved MATTHEW NELSON