3200 S GRAND AVE 90007

Certificate Information: 3200 S GRAND AVE 90007

Application / Permit
19016-20000-36285
Plan Check / Job No.
B19VN19536
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Nursery plant
Work Description
CHANGE OF USE FROM MANUFACTURING/OFFICE/RETAIL/STORAGE BUILDING TO INDOOR NURSERY (EXISTING NFPA-13 FIRE SPRINKLERS THROUGHOUT & NO EXTRACTION)
Permit Issued
Issued on 3/13/2020
Issuing Office
Metro
Current Status
Issued on 3/13/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 NILOOFAR MEHRAIN
Corrections Issued 11/18/2019 NILOOFAR MEHRAIN
Quality Review Completed 11/20/2019 GUANG MIN TUNG
Building Plans Picked Up 11/27/2019 APPLICANT
Disabled Access Plans Picked Up 11/27/2019 APPLICANT
Plan Check Approved 3/11/2020 NILOOFAR MEHRAIN
Issued 3/13/2020 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/16/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 12/16/2019 MARKOS PEREZ-BRAN
Community Plan Implem. Overlay Cleared 1/15/2020 TERRI OSBORNE
Community Plan Implem. Overlay Cleared 1/21/2020 EMIL KYUPELYAN
Redevelopment Project Area Cleared 1/21/2020 GISELLE CORELLA
ZI Cleared 1/21/2020 GISELLE CORELLA
Fire Marshall Fire Life Safety Cleared 1/23/2020 VIDAL GARCIA
DAS Clearance Cleared 1/28/2020 NILOOFAR MEHRAIN

Contact Information

Contractor Revive Contractors Group Llc; Lic. No.: 1034907-B 1560 COACHWOOD ST      LA HABRA, CA 90631

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/27/2020 Not Ready for Inspection LANNY MERRICK
Insulation 3/31/2020 No Access for Inspection RAFAEL ESPINOZA
Partition/T-Bar Ceiling 3/31/2020 No Access for Inspection RAFAEL ESPINOZA
Wood Frame 3/31/2020 No Access for Inspection RAFAEL ESPINOZA
Insulation 7/16/2020 Approved LANNY MERRICK
Light Gage Steel Frame 7/16/2020 Partial Approval LANNY MERRICK
Pre-Inspection 11/23/2020 Partial Inspection LEOPOLDO MENDOZA
Drywall Nailing 12/3/2020 Partial Approval LANNY MERRICK