344 E 57TH ST 90011
Certificate Information: 344 E 57TH ST 90011
- Application / Permit
- 19016-20000-36221
- Plan Check / Job No.
- B19VN19501
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' PORTION OF GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2019 | RAPHAEL ROSAS |
| Corrections Issued | 11/10/2019 | RAPHAEL ROSAS |
| Building Plans Picked Up | 11/14/2019 | APPLICANT |
| Plan Check Approved | 3/13/2020 | RAPHAEL ROSAS |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 1/12/2021 | MEL KHACHATOURIAN |
| Permit Finaled | 2/23/2021 | BRUCE TODD |
| CofO Issued | 2/23/2021 | BRUCE TODD |
| Permit Finaled | 2/23/2021 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 11/18/2019 | MARKOS PEREZ-BRAN |
| Community Plan Implem. Overlay | Cleared | 11/18/2019 | MARITZA PRZEKOP |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2019 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 11/18/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 11/18/2019 | MARKOS PEREZ-BRAN |
| ZI | Cleared | 11/18/2019 | MARITZA PRZEKOP |
| Construction near power lines | Cleared | 1/17/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/13/2020 | Not Ready for Inspection | HECTOR RODRIGUEZ |
| Green Building Rough | 4/13/2020 | Not Ready for Inspection | HECTOR RODRIGUEZ |
| Footing/Foundation/Slab | 4/22/2020 | Partial Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 4/28/2020 | Corrections Issued | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/6/2020 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/6/2020 | Partial Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 5/6/2020 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/12/2020 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/22/2020 | Partial Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 5/22/2020 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/12/2020 | Corrections Issued | MARIO CUEVAS |
| HVAC-Rough | 6/12/2020 | Corrections Issued | MARIO CUEVAS |
| PLUMBING-Rough | 6/12/2020 | Corrections Issued | MARIO CUEVAS |
| Underground Mechanical | 6/16/2020 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 6/26/2020 | Partial Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Partial Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/26/2020 | Partial Inspection | MEL KHACHATOURIAN |
| Gas Test | 7/7/2020 | Approved | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 7/7/2020 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 8/6/2020 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 8/6/2020 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Insulation | 8/6/2020 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/6/2020 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 8/13/2020 | Approved | MARIO CUEVAS |
| Drywall Nailing | 8/19/2020 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/21/2020 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/2/2020 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 10/2/2020 | Approved | MEL KHACHATOURIAN |
| Final | 10/5/2020 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Final | 10/5/2020 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2020 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Service/Power Release | 10/5/2020 | Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 10/5/2020 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 11/2/2020 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2020 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 11/2/2020 | Approved | MEL KHACHATOURIAN |
| Gas Test | 11/13/2020 | Approved | MEL KHACHATOURIAN |
| Final | 1/11/2021 | Conditional Approval | MEL KHACHATOURIAN |