10918-10920 N MCVINE AVE 91040
Certificate Information: 10918-10920 N MCVINE AVE 91040
- Application / Permit
- 19016-20000-36186
- Plan Check / Job No.
- B19VN19479
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT A PORTION (IRR 16'-3" X 11'-10") OF (E) SFD & (E) 22'6"X18'2" IRREGULAR SHAPED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER WFPP
- Permit Issued
- Issued on 11/12/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/8/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/8/2019 | MARVEL DELACRUZ |
| Issued | 11/12/2019 | LADBS |
| CofO in Progress | 3/9/2020 | MATTHEW NELSON |
| CofO in Progress | 3/9/2020 | MATTHEW NELSON |
| CofO Issued | 11/14/2020 | MICHAEL SMITH |
| Permit Finaled | 11/14/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/8/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2019 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 11/8/2019 | NILOOFAR MEHRAIN |
| Sewer availability | Cleared | 11/8/2019 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/19/2019 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/20/2019 | Approved | MATTHEW NELSON |
| Underground Mechanical | 12/20/2019 | Partial Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/30/2019 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/30/2019 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/2/2020 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/2/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 1/2/2020 | Approved | MATTHEW NELSON |
| Insulation | 1/15/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/15/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/21/2020 | Approved | MATTHEW NELSON |
| Final | 2/28/2020 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 2/28/2020 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/28/2020 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 2/28/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/6/2020 | Approved | MATTHEW NELSON |
| Final | 3/6/2020 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 3/6/2020 | Approved | MATTHEW NELSON |
| HVAC-Final | 3/6/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 3/6/2020 | Approved | MATTHEW NELSON |
| Final | 3/9/2020 | OK to Issue CofO | MATTHEW NELSON |