10918-10920 N MCVINE AVE 91040

Certificate Information: 10918-10920 N MCVINE AVE 91040

Application / Permit
19016-20000-36186
Plan Check / Job No.
B19VN19479
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT A PORTION (IRR 16'-3" X 11'-10") OF (E) SFD & (E) 22'6"X18'2" IRREGULAR SHAPED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER WFPP
Permit Issued
Issued on 11/12/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/8/2019 NILOOFAR MEHRAIN
Corrections Issued 11/8/2019 NILOOFAR MEHRAIN
Plan Check Approved 11/8/2019 MARVEL DELACRUZ
Issued 11/12/2019 LADBS
CofO in Progress 3/9/2020 MATTHEW NELSON
CofO in Progress 3/9/2020 MATTHEW NELSON
CofO Issued 11/14/2020 MICHAEL SMITH
Permit Finaled 11/14/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/8/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/8/2019 LEE GUILBEAUX
Grading Pre-Inspection Cleared 11/8/2019 NILOOFAR MEHRAIN
Sewer availability Cleared 11/8/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/19/2019 Approved MATTHEW NELSON
Footing/Foundation/Slab 12/20/2019 Approved MATTHEW NELSON
Underground Mechanical 12/20/2019 Partial Inspection MATTHEW NELSON
ELECTRICAL-Rough 12/30/2019 Approved MICHEL ABAJAN
PLUMBING-Rough 12/30/2019 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/2/2020 Approved MATTHEW NELSON
Green Building Rough 1/2/2020 Approved MATTHEW NELSON
HVAC-Rough 1/2/2020 Approved MATTHEW NELSON
Insulation 1/15/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/15/2020 Approved MATTHEW NELSON
Drywall Nailing 1/21/2020 Approved MATTHEW NELSON
Final 2/28/2020 Corrections Issued MATTHEW NELSON
Green Building Final 2/28/2020 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/28/2020 SGSOV Approved MATTHEW NELSON
Smoke Detectors 2/28/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 3/6/2020 Approved MATTHEW NELSON
Final 3/6/2020 OK to Issue CofO MATTHEW NELSON
Green Building Final 3/6/2020 Approved MATTHEW NELSON
HVAC-Final 3/6/2020 Approved MATTHEW NELSON
PLUMBING-Final 3/6/2020 Approved MATTHEW NELSON
Final 3/9/2020 OK to Issue CofO MATTHEW NELSON