220 S ALVARADO ST 90057

Certificate Information: 220 S ALVARADO ST 90057

Application / Permit
19016-20000-35725
Plan Check / Job No.
B19VN19260
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment Hotel
Work Description
CONVERT (11) EXISTING GUEST ROOMS/(12) DWELLING UNITS INTO (11) LIGHT HOUSEKEEPING UNITS & ADD (11) APT UNITS AT WEST PORTION OF BUILDING & CONVERT (15) EXISTING GUEST ROOMS INTO (15) LIGHT HOUSEKEEPING UNITS & ADD (3) UNITS AT EAST PORTION OF BUILDING CREATING A 26-UNIT APT BLDG W/ 26-LIGHT HOUSEKEEPING UNITS (35PKG SP REQ'D/39SP PROVIDED)
Permit Issued
Issued on 6/15/2021
Issuing Office
Current Status
Issued on 3/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/5/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 NILOOFAR MEHRAIN
Green Plans Picked Up 11/14/2019 APPLICANT
Corrections Issued 11/18/2019 NILOOFAR MEHRAIN
Quality Review Completed 11/20/2019 GUANG MIN TUNG
Disabled Access Plans Picked Up 11/21/2019 APPLICANT
Applicant returned to address corrections 4/9/2021 NILOOFAR MEHRAIN
Plan Check Approved 5/12/2021 NILOOFAR MEHRAIN
Issued 6/15/2021 APPLICANT
Building Plans Picked Up 6/18/2021 APPLICANT
No Progress 3/5/2024 RAFAEL ESPINOZA
TCO Issued (Expire Date: 11-10-2024) 5/14/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 07-08-2025) 1/9/2025 ERNESTO CORRAL
TCO Issued (Expire Date: 12-09-2025) 6/12/2025 JOEY BUCHANAN
TCO Issued (Expire Date: 06-02-2026) 12/4/2025 RAFAEL ESPINOZA
TCO Issued (Expire Date: 12-01-2026) 6/4/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 1/15/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/15/2020 LEE GUILBEAUX
Highway dedication Cleared 1/15/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/15/2020 LEE GUILBEAUX
Sewer availability Cleared 1/15/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 1/21/2020 GILBERT URREA
Green Code Cleared 1/27/2020 DAVID MATSON
DAS Clearance Cleared 7/29/2020 NILOOFAR MEHRAIN
Residential hotels Cleared 10/2/2020 MARITES CUNANAN
ZI Cleared 10/7/2020 LAUREN PADICK
Fire Marshall Fire Life Safety Cleared 3/11/2021 OSCAR SALGADO JR
ZA Case Cleared 4/21/2021 DENZEL HENDERSON
ZA Case Cleared 4/21/2021 DENZEL HENDERSON

Contact Information

Contractor Caribe Construction Inc; Lic. No.: 878090-B 521 S PARISH PLACE      BURBANK, CA 91506
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/17/2022 Partial Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 4/25/2022 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 4/26/2022 Corrections Issued RAFAEL ESPINOZA
Green Building Rough 4/26/2022 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 4/26/2022 Approved RAFAEL ESPINOZA
Wood Frame 4/26/2022 Conditional Approval RAFAEL ESPINOZA
Insulation 5/16/2022 Partial Approval TIMOTHY BUXTON
Footing/Foundation/Slab 6/15/2022 Partial Approval TIMOTHY BUXTON
Drywall Nailing 9/12/2022 Partial Approval TIMOTHY BUXTON
Green Building Rough 11/18/2022 Approved TIMOTHY BUXTON
Insulation 11/18/2022 Approved TIMOTHY BUXTON
Wood Frame 11/18/2022 Corrections Issued TIMOTHY BUXTON
Wood Frame 11/22/2022 Corrections Issued RONALD JIMENEZ
Wood Frame 12/1/2022 Partial Approval TIMOTHY BUXTON
Drywall Nailing 12/15/2022 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 12/16/2022 Partial Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 3/17/2023 Partial Approval NICK DANERI
Wood Frame 3/31/2023 Approved RAMAZANALI ALMASI
Insulation 4/12/2023 Approved RAMAZANALI ALMASI
Interior/Exterior Lathing 4/13/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 4/25/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 4/28/2023 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Not Ready for Inspection JEROME BLACKWOOD
Insulation 6/7/2023 Not Ready for Inspection JEROME BLACKWOOD
Insulation 7/5/2023 Not Ready for Inspection RAMAZANALI ALMASI
Final 11/8/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 11/8/2023 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 11/8/2023 Not Ready for Inspection JEROME BLACKWOOD
Final 1/26/2024 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 1/26/2024 Not Ready for Inspection JEROME BLACKWOOD
Smoke Detectors 1/26/2024 Approved JEROME BLACKWOOD
Final 3/4/2024 Conditional Approval JEROME BLACKWOOD
Green Building Final 3/4/2024 Approved JEROME BLACKWOOD
Final 3/7/2024 Not Ready for Inspection JEROME BLACKWOOD
Special/Order Compliance 3/19/2024 Corrections Issued JEROME BLACKWOOD
Special/Order Compliance 10/21/2024 Partial Inspection JEROME BLACKWOOD
Special/Order Compliance 6/10/2025 Partial Inspection JEROME BLACKWOOD
Special/Order Compliance 11/4/2025 Partial Approval JEROME BLACKWOOD
Special/Order Compliance 11/13/2025 Not Ready for Inspection DARRYL ARNOLD
Special/Order Compliance 5/11/2026 Partial Inspection REGINA MENDEZ