5907 E EUCALYPTUS LANE 90042
Certificate Information: 5907 E EUCALYPTUS LANE 90042
- Application / Permit
- 19016-20000-35284
- Plan Check / Job No.
- B19VN19025
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW (24'-8 1/4"x 27'-8 1/2") IRR. SHAPE RAISED DECK ADDITION TO (E) ACCESSOR LIVING QUARTERS. WORK PER ENGINEER.
- Permit Issued
- Issued on 1/15/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/2/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | TROY DEGUZMAN |
| Corrections Issued | 11/20/2019 | TROY DEGUZMAN |
| Quality Review Completed | 11/20/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 11/21/2019 | APPLICANT |
| Applicant returned to address corrections | 12/30/2019 | TROY DEGUZMAN |
| Plan Check Approved | 1/9/2020 | TROY DEGUZMAN |
| Issued | 1/15/2020 | LADBS |
| CofO in Progress | 7/21/2020 | CRAIG VAUGHAN |
| Permit Finaled | 9/2/2020 | DEROLD HAUFF |
| CofO Issued | 9/2/2020 | DEROLD HAUFF |
| Permit Finaled | 9/2/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 12/16/2019 | APEKSHYA BAJRACHARYA |
| GPI Written Notices | Cleared | 12/30/2019 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 12/30/2019 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mills,, Garrett Ward; Lic. No.: S5271 | 553 S OAK KNOLL AVE PASADENA, CA 91101 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/23/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/21/2020 | Approved | CRAIG VAUGHAN |
| Deck | 5/21/2020 | Approved | CRAIG VAUGHAN |
| Wood Frame | 5/21/2020 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/20/2020 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 7/20/2020 | Approved | CRAIG VAUGHAN |
| Final | 7/20/2020 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 7/20/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 7/20/2020 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 7/20/2020 | Approved | CRAIG VAUGHAN |