23855-23857 W CALIFA ST 91367

Certificate Information: 23855-23857 W CALIFA ST 91367

Application / Permit
19016-20000-35211
Plan Check / Job No.
B19VN18974
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT AND ENCLOSE FRONT PORCH TO EXPAND DWELLING FOYER.
Permit Issued
Issued on 1/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/1/2019 ANGELICA DAVE
Corrections Issued 11/1/2019 ANGELICA DAVE
Plan Check Approved 1/3/2020 ALDOUS CHIC
Issued 1/3/2020 LADBS
CofO in Progress 7/21/2020 TROY SANDERS
Permit Finaled 7/21/2020 JOHN JANSON
CofO Issued 7/21/2020 JOHN JANSON
Permit Finaled 7/21/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/1/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/1/2019 ADRIAN CASTRO
Grading Pre-Inspection Cleared 11/1/2019 BARTON HOLMES
Sewer availability Cleared 11/1/2019 ADRIAN CASTRO
Construction near power lines Cleared 12/23/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/19/2020 Not Ready for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 2/19/2020 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 2/19/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 2/19/2020 Partial Approval JOHN KIDWELL
Underground Mechanical 2/19/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 3/2/2020 Approved JOHN KIDWELL
BUILDING-Rough-Frame 3/11/2020 Approved JOHN KIDWELL
Green Building Rough 3/11/2020 Approved JOHN KIDWELL
Rough-Elec/Plmb/HVAC 3/11/2020 Approved JOHN KIDWELL
Shower Pan 3/11/2020 Approved JOHN KIDWELL
Drywall Nailing 3/17/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/17/2020 Partial Approval JOHN KIDWELL
Gas Test 3/27/2020 Approved JOHN KIDWELL
Final 5/5/2020 Not Ready for Inspection JOHN KIDWELL
Green Building Final 5/5/2020 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/5/2020 SGSOV Gas Company JOHN KIDWELL
Smoke Detectors 5/5/2020 Approved JOHN KIDWELL
ELECTRICAL-Final 7/6/2020 Approved TROY SANDERS
Final 7/6/2020 Corrections Issued TROY SANDERS
Green Building Final 7/6/2020 Corrections Issued TROY SANDERS
HVAC-Final 7/6/2020 Approved TROY SANDERS
PLUMBING-Final 7/6/2020 Approved TROY SANDERS
Final 7/21/2020 OK to Issue CofO TROY SANDERS
Green Building Final 7/21/2020 Approved TROY SANDERS