7632 N KRAFT AVE 91605

Certificate Information: 7632 N KRAFT AVE 91605

Application / Permit
19016-20000-35080
Plan Check / Job No.
B19VN18903
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED RECREATION ROOM/STORAGE ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 12/16/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/1/2019 ALDOUS CHIC
Corrections Issued 11/1/2019 ALDOUS CHIC
Plan Check Approved 12/12/2019 RAPHAEL ROSAS
Issued 12/16/2019 LADBS
CofO in Progress 4/7/2025 MATTHEW NELSON
Permit Finaled 4/15/2025 RUBEN SALAS
CofO Issued 4/15/2025 RUBEN SALAS
Permit Finaled 4/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/1/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 11/1/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 11/1/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/21/2020 Corrections Issued JOHN HAYES
Special/Order Compliance 2/12/2020 Corrections Issued JOHN HAYES
PLUMBING-Rough 11/2/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/10/2020 Corrections Issued JOHN HAYES
PLUMBING-Rough 11/16/2020 Not Ready for Inspection JOHN HAYES
Underground Mechanical 11/19/2020 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 6/10/2021 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 6/16/2021 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 6/21/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 3/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/3/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/10/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/10/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Wood Frame 3/10/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/21/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/24/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/12/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/22/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/17/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Insulation 5/17/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Shower Pan 5/17/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Pre-Inspection 12/23/2022 Corrections Issued MATTHEW NELSON
Pre-Inspection 1/11/2023 Corrections Issued MATTHEW NELSON
Wood Frame 3/23/2023 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 6/1/2023 Approved MATTHEW NELSON
HVAC-Rough 6/1/2023 Approved MATTHEW NELSON
Insulation 6/6/2023 Approved WILLIAM WREN
Shower Pan 6/6/2023 Approved WILLIAM WREN
Drywall Nailing 7/27/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/27/2023 Approved MATTHEW NELSON
Final 7/11/2024 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Approved DAVID ANDERSON
Smoke Detectors 7/11/2024 Approved DAVID ANDERSON
Final 7/26/2024 Partial Approval MATTHEW NELSON
Final 4/7/2025 OK to Issue CofO MATTHEW NELSON