14873-14875 W LA VALLE ST 91342
Certificate Information: 14873-14875 W LA VALLE ST 91342
- Application / Permit
- 19016-20000-35042
- Plan Check / Job No.
- B19VN18886
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert attached garage to Accessory Dwelling Unit per AB 494 & SB 229
- Permit Issued
- Issued on 11/1/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | ANGELICA DAVE |
| Corrections Issued | 10/31/2019 | ANGELICA DAVE |
| Plan Check Approved | 10/31/2019 | ALDOUS CHIC |
| Issued | 11/1/2019 | LADBS |
| CofO in Progress | 8/31/2021 | MISAEL ESPARZA |
| CofO Issued | 10/14/2021 | MICHAEL SMITH |
| Permit Finaled | 10/14/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/31/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/31/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/25/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 1/27/2021 | Approved | MISAEL ESPARZA |
| Sewer | 1/27/2021 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/4/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 2/4/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/8/2021 | Partial Inspection | MISAEL ESPARZA |
| Green Building Rough | 2/8/2021 | Partial Inspection | MISAEL ESPARZA |
| Pre-Inspection | 2/8/2021 | Partial Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/10/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 2/10/2021 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/23/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/23/2021 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/23/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 2/23/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 2/23/2021 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/11/2021 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 3/11/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/25/2021 | No Access for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/6/2021 | Partial Approval | MISAEL ESPARZA |
| Insulation | 4/15/2021 | Partial Approval | MISAEL ESPARZA |
| Insulation | 5/12/2021 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/4/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 6/4/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/18/2021 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 6/18/2021 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 6/18/2021 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 6/18/2021 | Approved | MISAEL ESPARZA |
| Insulation | 6/18/2021 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 7/19/2021 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 8/20/2021 | Corrections Issued | MISAEL ESPARZA |
| Final | 8/20/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 8/20/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 8/20/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 8/20/2021 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/20/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/27/2021 | Approved | MISAEL ESPARZA |
| Final | 8/27/2021 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 8/27/2021 | Approved | MISAEL ESPARZA |
| HVAC-Final | 8/27/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 8/27/2021 | Approved | MISAEL ESPARZA |