14873-14875 W LA VALLE ST 91342

Certificate Information: 14873-14875 W LA VALLE ST 91342

Application / Permit
19016-20000-35042
Plan Check / Job No.
B19VN18886
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert attached garage to Accessory Dwelling Unit per AB 494 & SB 229
Permit Issued
Issued on 11/1/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 ANGELICA DAVE
Corrections Issued 10/31/2019 ANGELICA DAVE
Plan Check Approved 10/31/2019 ALDOUS CHIC
Issued 11/1/2019 LADBS
CofO in Progress 8/31/2021 MISAEL ESPARZA
CofO Issued 10/14/2021 MICHAEL SMITH
Permit Finaled 10/14/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/31/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/31/2019 ADRIAN CASTRO
Sewer availability Cleared 10/31/2019 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/25/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 1/27/2021 Approved MISAEL ESPARZA
Sewer 1/27/2021 Approved MISAEL ESPARZA
Footing/Foundation/Slab 2/4/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/4/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 2/8/2021 Partial Inspection MISAEL ESPARZA
Green Building Rough 2/8/2021 Partial Inspection MISAEL ESPARZA
Pre-Inspection 2/8/2021 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 2/10/2021 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 2/10/2021 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/23/2021 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/23/2021 Approved MISAEL ESPARZA
Footing/Foundation/Slab 2/23/2021 Approved MISAEL ESPARZA
Green Building Rough 2/23/2021 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 2/23/2021 Approved MISAEL ESPARZA
Footing/Foundation/Slab 3/11/2021 Approved MISAEL ESPARZA
Pre-Inspection 3/11/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/25/2021 No Access for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 4/6/2021 Partial Approval MISAEL ESPARZA
Insulation 4/15/2021 Partial Approval MISAEL ESPARZA
Insulation 5/12/2021 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 6/4/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 6/4/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/18/2021 Approved MISAEL ESPARZA
Drywall Nailing 6/18/2021 Partial Approval MISAEL ESPARZA
Green Building Rough 6/18/2021 Approved MISAEL ESPARZA
HVAC-Rough 6/18/2021 Approved MISAEL ESPARZA
Insulation 6/18/2021 Approved MISAEL ESPARZA
Drywall Nailing 7/19/2021 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 8/20/2021 Corrections Issued MISAEL ESPARZA
Final 8/20/2021 Corrections Issued MISAEL ESPARZA
Green Building Final 8/20/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 8/20/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 8/20/2021 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/20/2021 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 8/20/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 8/27/2021 Approved MISAEL ESPARZA
Final 8/27/2021 OK to Issue CofO MISAEL ESPARZA
Green Building Final 8/27/2021 Approved MISAEL ESPARZA
HVAC-Final 8/27/2021 Approved MISAEL ESPARZA
PLUMBING-Final 8/27/2021 Approved MISAEL ESPARZA