8521-8523 N MELVIN AVE 91324

Certificate Information: 8521-8523 N MELVIN AVE 91324

Application / Permit
19016-20000-34891
Plan Check / Job No.
B19VN18806
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 3/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2019 APPLICANT
Assigned to Plan Check Engineer 10/30/2019 JEFFREY TANGONAN
Corrections Issued 10/30/2019 JEFFREY TANGONAN
Building Plans Picked Up 11/6/2019 APPLICANT
Plan Check Approved 12/17/2019 JEFFREY TANGONAN
Issued 3/13/2020 LADBS
CofO in Progress 8/3/2020 JEFFREY PARD
CofO Issued 8/3/2020 JOHN JANSON
Permit Finaled 8/3/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/6/2019 LEE GUILBEAUX
Sewer availability Cleared 11/6/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/5/2019 CHRISTINE REUSCH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/16/2020 Approved HENRY KIM
Footing/Foundation/Slab 4/16/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 4/20/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 4/28/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 4/28/2020 Not Ready for Inspection VINCENT HANLEY
Wood Frame 4/28/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 4/30/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/4/2020 Approved HENRY KIM
Footing/Foundation/Slab 5/4/2020 Approved HENRY KIM
BUILDING-Rough-Frame 5/6/2020 Partial Approval JOHN KIDWELL
Green Building Rough 5/6/2020 Not Ready for Inspection JOHN KIDWELL
Insulation 5/6/2020 Partial Approval JOHN KIDWELL
Wood Frame 5/12/2020 Partial Approval JOHN KIDWELL
Drywall Nailing 5/19/2020 Not Ready for Inspection DONALD SUNSERI
Shower Pan 5/19/2020 Approved DONALD SUNSERI
Interior/Exterior Lathing 5/20/2020 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 5/26/2020 Approved MICHAEL TEMPLE
Drywall Nailing 5/26/2020 Conditional Approval MICHAEL TEMPLE
Green Building Rough 5/26/2020 Approved MICHAEL TEMPLE
Interior/Exterior Lathing 5/26/2020 Approved MICHAEL TEMPLE
Drywall Nailing 7/22/2020 Approved JEFFREY PARD
Final 7/22/2020 Not Ready for Inspection JEFFREY PARD
Green Building Final 7/22/2020 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 7/22/2020 SGSOV Approved JEFFREY PARD
Smoke Detectors 7/22/2020 Approved JEFFREY PARD
Final 7/27/2020 No Access for Inspection JEFFREY PARD
Green Building Final 7/27/2020 No Access for Inspection JEFFREY PARD
Final 7/29/2020 Corrections Issued JEFFREY PARD
Final 7/31/2020 OK to Issue CofO JEFFREY PARD
Green Building Final 7/31/2020 Approved JEFFREY PARD