7267 N HATILLO AVE 91306
Certificate Information: 7267 N HATILLO AVE 91306
- Application / Permit
- 19016-20000-34789
- Plan Check / Job No.
- B19VN18748
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-3" X 20'-0" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | JENNIFER LEE |
| Corrections Issued | 11/1/2019 | JENNIFER LEE |
| Building Plans Picked Up | 11/1/2019 | APPLICANT |
| Plan Check Approved | 11/19/2019 | JENNIFER LEE |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 7/31/2020 | HENRY KIM |
| CofO Issued | 8/3/2020 | JOHN JANSON |
| Permit Finaled | 8/3/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/5/2019 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 11/6/2019 | OSCAR CASTRO |
| Construction within easement | Cleared | 11/6/2019 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | Igreen Remodeling Inc; Lic. No.: 1047582-B | 8549 WILSHIRE BLVD #1263 BEVERLY HILLS, CA 90211 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/3/2020 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 4/23/2020 | Not Ready for Inspection | HENRY KIM |
| Footing/Foundation/Slab | 4/24/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 5/18/2020 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 5/18/2020 | Approved | HENRY KIM |
| Green Building Rough | 5/18/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 5/18/2020 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 5/20/2020 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 5/20/2020 | Not Ready for Inspection | HENRY KIM |
| Rough-Elec/Plmb/HVAC | 5/20/2020 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 5/27/2020 | Partial Approval | HENRY KIM |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 5/27/2020 | Approved | HENRY KIM |
| Sewer | 5/27/2020 | Approved | HENRY KIM |
| Underground Mechanical | 5/27/2020 | Approved | HENRY KIM |
| Insulation | 6/5/2020 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2020 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 6/9/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Approved | HENRY KIM |
| Green Building Rough | 6/9/2020 | Approved | HENRY KIM |
| Insulation | 6/9/2020 | Approved | HENRY KIM |
| Drywall Nailing | 6/19/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 6/19/2020 | Not Ready for Inspection | HENRY KIM |
| Green Building Final | 7/21/2020 | Not Ready for Inspection | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 7/21/2020 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 7/21/2020 | Not Ready for Inspection | HENRY KIM |
| Interior/Exterior Lathing | 7/22/2020 | Approved | HENRY KIM |
| Final | 7/23/2020 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Final | 7/29/2020 | Corrections Issued | HENRY KIM |
| Final | 7/29/2020 | Corrections Issued | HENRY KIM |
| Gas Test | 7/29/2020 | Corrections Issued | HENRY KIM |
| Green Building Final | 7/29/2020 | Approved | HENRY KIM |
| HVAC-Final | 7/29/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 7/29/2020 | Corrections Issued | HENRY KIM |
| Smoke Detectors | 7/29/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 7/31/2020 | Approved | HENRY KIM |
| Final | 7/31/2020 | OK to Issue CofO | HENRY KIM |
| Gas Test | 7/31/2020 | Approved | HENRY KIM |
| HVAC-Final | 7/31/2020 | Approved | HENRY KIM |
| PLUMBING-Final | 7/31/2020 | Approved | HENRY KIM |