7267 N HATILLO AVE 91306

Certificate Information: 7267 N HATILLO AVE 91306

Application / Permit
19016-20000-34789
Plan Check / Job No.
B19VN18748
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-3" X 20'-0" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 1/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 JENNIFER LEE
Corrections Issued 11/1/2019 JENNIFER LEE
Building Plans Picked Up 11/1/2019 APPLICANT
Plan Check Approved 11/19/2019 JENNIFER LEE
Issued 1/17/2020 LADBS
CofO in Progress 7/31/2020 HENRY KIM
CofO Issued 8/3/2020 JOHN JANSON
Permit Finaled 8/3/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/5/2019 ADRIAN CASTRO
Sewer availability Cleared 11/5/2019 ADRIAN CASTRO
Construction near power lines Cleared 11/6/2019 OSCAR CASTRO
Construction within easement Cleared 11/6/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 1/17/2020 LEE GUILBEAUX

Contact Information

Contractor Igreen Remodeling Inc; Lic. No.: 1047582-B 8549 WILSHIRE BLVD #1263      BEVERLY HILLS, CA 90211

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/3/2020 Partial Approval HENRY KIM
Footing/Foundation/Slab 4/23/2020 Not Ready for Inspection HENRY KIM
Footing/Foundation/Slab 4/24/2020 Approved HENRY KIM
BUILDING-Rough-Frame 5/18/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 5/18/2020 Approved HENRY KIM
Green Building Rough 5/18/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 5/18/2020 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 5/20/2020 Not Ready for Inspection HENRY KIM
Green Building Rough 5/20/2020 Not Ready for Inspection HENRY KIM
Rough-Elec/Plmb/HVAC 5/20/2020 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 5/27/2020 Partial Approval HENRY KIM
Green Building Rough 5/27/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 5/27/2020 Approved HENRY KIM
Sewer 5/27/2020 Approved HENRY KIM
Underground Mechanical 5/27/2020 Approved HENRY KIM
Insulation 6/5/2020 Partial Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 6/9/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Approved HENRY KIM
Green Building Rough 6/9/2020 Approved HENRY KIM
Insulation 6/9/2020 Approved HENRY KIM
Drywall Nailing 6/19/2020 Approved HENRY KIM
Interior/Exterior Lathing 6/19/2020 Not Ready for Inspection HENRY KIM
Green Building Final 7/21/2020 Not Ready for Inspection HENRY KIM
SGSOV-Seismic Gas S/O Valve 7/21/2020 SGSOV Approved HENRY KIM
Smoke Detectors 7/21/2020 Not Ready for Inspection HENRY KIM
Interior/Exterior Lathing 7/22/2020 Approved HENRY KIM
Final 7/23/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 7/29/2020 Corrections Issued HENRY KIM
Final 7/29/2020 Corrections Issued HENRY KIM
Gas Test 7/29/2020 Corrections Issued HENRY KIM
Green Building Final 7/29/2020 Approved HENRY KIM
HVAC-Final 7/29/2020 Corrections Issued HENRY KIM
PLUMBING-Final 7/29/2020 Corrections Issued HENRY KIM
Smoke Detectors 7/29/2020 Approved HENRY KIM
ELECTRICAL-Final 7/31/2020 Approved HENRY KIM
Final 7/31/2020 OK to Issue CofO HENRY KIM
Gas Test 7/31/2020 Approved HENRY KIM
HVAC-Final 7/31/2020 Approved HENRY KIM
PLUMBING-Final 7/31/2020 Approved HENRY KIM