3527 S GREENFIELD AVE 90034
Certificate Information: 3527 S GREENFIELD AVE 90034
- Application / Permit
- 19016-20000-34710
- Plan Check / Job No.
- B19VN18696
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'9" X 19'9" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/26/2019
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 12/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2019 | ALDOUS CHIC |
| Corrections Issued | 10/29/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 11/26/2019 | YAQUB MIRZA |
| Plan Check Approved | 11/26/2019 | RARES BODEA |
| Issued | 11/26/2019 | LADBS |
| CofO in Progress | 12/1/2020 | KENNETH NAGLE |
| CofO Issued-Status Void | 12/2/2020 | VINCENT COTTON |
| Permit Finaled-Status Void | 12/2/2020 | VINCENT COTTON |
| Re-Activate Permit | 12/4/2020 | VINCENT COTTON |
| Permit Finaled | 12/9/2020 | VINCENT COTTON |
| CofO Corrected | 12/9/2020 | VINCENT COTTON |
| Permit Finaled | 12/9/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2019 | JOHN LIN |
| Sewer availability | Cleared | 10/29/2019 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 11/26/2019 | ALDOUS CHIC |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Estrada,, Jorge; Lic. No.: C87410 | 1344 CLAREMONT PLACE POMONA, CA 91767 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/14/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 5/14/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/11/2020 | Partial Approval | JUSTIN CURTIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Partial Approval | JUSTIN CURTIS |
| Green Building Rough | 6/11/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| PLUMBING-Rough | 6/11/2020 | Partial Approval | JUSTIN CURTIS |
| Sewer | 6/11/2020 | Approved | JUSTIN CURTIS |
| ELECTRICAL-Rough | 7/2/2020 | Approved | JUSTIN CURTIS |
| Gas Test | 7/2/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| HVAC-Rough | 7/2/2020 | Approved | JUSTIN CURTIS |
| PLUMBING-Rough | 7/2/2020 | Approved | JUSTIN CURTIS |
| Wood Frame | 7/2/2020 | Conditional Approval | JUSTIN CURTIS |
| Insulation | 7/13/2020 | Approved | JUSTIN CURTIS |
| Deputy Wood Construction | 7/17/2020 | Approved | JUSTIN CURTIS |
| Drywall Nailing | 7/17/2020 | Approved | JUSTIN CURTIS |
| Interior/Exterior Lathing | 7/22/2020 | Approved | JUSTIN CURTIS |
| Shower Pan | 7/22/2020 | Approved | JUSTIN CURTIS |
| Gas Test | 7/24/2020 | Partial Approval | KENNETH NAGLE |
| Interior/Exterior Lathing | 8/4/2020 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/14/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/14/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 10/14/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 10/14/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 10/14/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 10/14/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 10/14/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/14/2020 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/12/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 11/12/2020 | Partial Approval | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 11/23/2020 | Not Ready for Inspection | RICHARD ROBLES |
| Service/Power Release | 11/23/2020 | Not Required | RICHARD ROBLES |
| Service/Power Release | 11/25/2020 | Approved | KENNETH NAGLE |