7936-7938 N CAPISTRANO AVE 91304
Certificate Information: 7936-7938 N CAPISTRANO AVE 91304
- Application / Permit
- 19016-20000-34548
- Plan Check / Job No.
- B19VN18557
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 22' ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2019 | ALDOUS CHIC |
| Corrections Issued | 10/28/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 10/30/2019 | JENNIFER LEE |
| Plan Check Approved | 1/17/2020 | LUIS RINCON |
| Issued | 1/29/2020 | LADBS |
| CofO in Progress | 7/1/2020 | DAVID STEPANYAN |
| CofO Issued | 11/29/2021 | MICHAEL SMITH |
| Permit Finaled | 11/29/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/28/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/31/2020 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 1/31/2020 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 1/31/2020 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 2/18/2020 | Partial Approval | HENRY KIM |
| Underground Mechanical | 2/18/2020 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 2/24/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Rough | 2/24/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 2/24/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 2/27/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 3/3/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 3/3/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 3/3/2020 | Partial Approval | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 3/9/2020 | Partial Approval | DAVID STEPANYAN |
| Interior/Exterior Lathing | 3/9/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Deputy Drilled-In Anchors | 3/10/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 3/11/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 3/16/2020 | Partial Approval | DAVID STEPANYAN |
| Drywall Nailing | 3/16/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Rough | 3/16/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 3/16/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 3/20/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 3/20/2020 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 3/26/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 3/26/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 3/26/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 3/26/2020 | Partial Approval | DAVID STEPANYAN |
| Insulation | 4/2/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 4/8/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 4/8/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 6/15/2020 | Approved | DAVID STEPANYAN |
| Final | 6/15/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 6/15/2020 | Approved | DAVID STEPANYAN |
| Final | 6/24/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Final | 6/24/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 6/24/2020 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 6/24/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 6/29/2020 | Approved | DAVID STEPANYAN |
| Final | 6/29/2020 | Partial Approval | DAVID STEPANYAN |
| Gas Test | 6/29/2020 | Approved | DAVID STEPANYAN |
| HVAC-Final | 6/29/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 6/29/2020 | Approved | DAVID STEPANYAN |
| Final | 6/30/2020 | OK to Issue CofO | DAVID STEPANYAN |