8927-8929 N BAIRD AVE 91324
Certificate Information: 8927-8929 N BAIRD AVE 91324
- Application / Permit
- 19016-20000-34059
- Plan Check / Job No.
- B19VN18299
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 10/23/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | ANGELICA DAVE |
| Corrections Issued | 10/23/2019 | ANGELICA DAVE |
| Plan Check Approved | 10/23/2019 | ANGELICA MARTINEZ |
| Issued | 10/23/2019 | LADBS |
| CofO in Progress | 1/28/2021 | JEFFREY PARD |
| Permit Finaled | 1/29/2021 | JOHN JANSON |
| CofO Issued | 1/29/2021 | JOHN JANSON |
| Permit Finaled | 1/29/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2019 | DYNL MIRANDA |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2019 | DYNL MIRANDA |
| Sewer availability | Cleared | 10/23/2019 | DYNL MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/4/2019 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/4/2019 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 12/5/2019 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 12/6/2019 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/28/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/28/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Gas Test | 1/28/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 1/28/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 1/28/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 1/28/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Sewer | 1/28/2020 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 1/28/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/5/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 2/5/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 2/5/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 2/5/2020 | Approved | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 2/5/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Wood Frame | 2/5/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/11/2020 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 2/11/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 2/11/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 2/11/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 2/18/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 2/18/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 2/18/2020 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 2/18/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 2/26/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2020 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 2/26/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Wood Frame | 2/26/2020 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 3/10/2020 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/10/2020 | Approved | DAVID SANDOVAL |
| Shower Pan | 3/10/2020 | Approved | DAVID SANDOVAL |
| Service/Power Release | 4/14/2020 | Partial Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/16/2020 | SGSOV Not Ready | HENRY KIM |
| BUILDING-Rough-Frame | 1/15/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 1/15/2021 | Approved | JEFFREY PARD |
| Final | 1/15/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 1/15/2021 | Approved | JEFFREY PARD |
| HVAC-Final | 1/15/2021 | Approved | JEFFREY PARD |
| PLUMBING-Final | 1/15/2021 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 1/15/2021 | SGSOV Approved | JEFFREY PARD |
| Service/Power Release | 1/15/2021 | Not Ready for Inspection | JEFFREY PARD |
| Smoke Detectors | 1/15/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 1/28/2021 | Approved | JEFFREY PARD |
| Final | 1/28/2021 | OK to Issue CofO | JEFFREY PARD |
| HVAC-Final | 1/28/2021 | Approved | JEFFREY PARD |
| PLUMBING-Final | 1/28/2021 | Approved | JEFFREY PARD |
| Service/Power Release | 1/28/2021 | Approved | JEFFREY PARD |