1625 S VINEYARD AVE 1-9 90019
Certificate Information: 1625 S VINEYARD AVE 1-9 90019
- Application / Permit
- 19016-20000-33756
- Plan Check / Job No.
- B19VN18128
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (1) APARTMENT UNIT INTO (2) UNITS IN 2ND STORY OF (E) APARTMENT BUILDING. NO STRUCTURAL CHANGES TO BE MADE. NFPA 13R FIRE SPRINKLERS TO BE PROVIDED.
- Permit Issued
- Issued on 1/10/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 11/7/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 11/12/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/21/2019 | APPLICANT |
| Applicant returned to address corrections | 1/9/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/10/2020 | GURUNATH NESARAJAH |
| Issued | 1/10/2020 | LADBS |
| CofO in Progress | 3/23/2021 | TIMOTHY BUXTON |
| Permit Finaled | 4/26/2021 | ERNESTO CORRAL |
| CofO Issued | 4/26/2021 | ERNESTO CORRAL |
| Permit Finaled | 4/26/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 11/21/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 11/21/2019 | APEKSHYA BAJRACHARYA |
| Housing rent stabilization | Cleared | 12/16/2019 | ISMAEL HERNANDEZ |
| Permit | Cleared | 12/30/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Calderon Alejandro; Lic. No.: 1020343-B | 5456 W 119 STREET INGLEWOOD, CA 90304 |
| Engineer | Mauricio,, Omar; Lic. No.: C87487 | 947 E MERCED AVE WEST COVINA, CA 91790 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 2/26/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| METHANE-Rough | 4/21/2020 | Approved | TIMOTHY BUXTON |
| Wood Frame | 4/21/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Wood Frame | 4/28/2020 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 5/19/2020 | Approved | TIMOTHY BUXTON |
| Insulation | 5/19/2020 | Approved | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 5/19/2020 | Approved | TIMOTHY BUXTON |
| Final | 7/28/2020 | Conditional Approval | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 7/28/2020 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 7/28/2020 | Approved | TIMOTHY BUXTON |
| Final | 11/13/2020 | Conditional Approval | TIMOTHY BUXTON |
| Final | 3/23/2021 | OK to Issue CofO | TIMOTHY BUXTON |