13230 W SATICOY ST 91605
Certificate Information: 13230 W SATICOY ST 91605
- Application / Permit
- 19016-20000-33460
- Plan Check / Job No.
- B19VN17971
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- TENANT IMPROVEMENTS TO (E) WAREHOUSE & OFFICE BUILDING: DEMO & INSTALL NON-BEARING WALLS AND SAW CUT SLAB AT DOCK
- Permit Issued
- Issued on 12/16/2019
- Issuing Office
- San Pedro
- Current Status
- Permit Finaled on 8/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2019 | APPLICANT |
| No Progress | 10/18/2019 | ZABEL ALTUNKARYAN |
| Green Plans Picked Up | 10/29/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 10/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/4/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/5/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/6/2019 | APPLICANT |
| Plan Check Approved | 12/5/2019 | NILOOFAR MEHRAIN |
| Issued | 12/16/2019 | LADBS |
| Permit Finaled | 8/4/2021 | ANDREW DORSO |
Permit Application Clearance Information
| DAS Clearance | Cleared | 11/18/2019 | NILOOFAR MEHRAIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2019 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 11/18/2019 | HERMINIGILDO AGUSTIN |
| Sewer availability | Cleared | 11/18/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 11/27/2019 | DAVID MATSON |
Contact Information
| Architect | Nam,, Yong Hwan; Lic. No.: C29451 | 18831 BARDEEN AVENUE # 100 IRVINE, CA 92612 |
| Contractor | Wilson Norm & Sons Inc; Lic. No.: 435700-B | 3400 EAST SPRING STREET LONG BEACH, CA 908062430 |
| Engineer | Fong,, Darin Gim; Lic. No.: S5188 | 20091 UMBRIA WAY YORBA LINDA, CA 92886 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/13/2020 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 4/14/2020 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 4/14/2020 | Corrections Issued | ANDREW DORSO |
| Deputy Reinf. Concrete | 4/15/2020 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 4/30/2020 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 4/30/2020 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 5/1/2020 | Partial Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 5/8/2020 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 5/11/2020 | Conditional Approval | ANDREW DORSO |
| Piling/Pier/Caisson | 5/13/2020 | Partial Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 5/15/2020 | Partial Inspection | ANDREW DORSO |
| Piling/Pier/Caisson | 5/15/2020 | Corrections Issued | ANDREW DORSO |
| Deputy Drilled-In Anchors | 6/5/2020 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 6/9/2020 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 6/9/2020 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 9/25/2020 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 9/28/2020 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 9/29/2020 | Conditional Approval | ANDREW DORSO |
| Pre-Inspection | 10/9/2020 | Corrections Issued | ANDREW DORSO |
| Wood Frame | 10/9/2020 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 10/13/2020 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 10/21/2020 | Conditional Approval | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 10/21/2020 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 10/23/2020 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 10/23/2020 | Partial Inspection | ANDREW DORSO |
| Reinforced Concrete Frame | 10/26/2020 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 11/10/2020 | Approved | ANDREW DORSO |
| Special/Order Compliance | 11/10/2020 | Corrections Issued | ANDREW DORSO |
| Footing/Foundation/Slab | 11/12/2020 | Partial Inspection | ANDREW DORSO |
| Insulation | 11/12/2020 | Approved | ANDREW DORSO |
| Deputy Drilled-In Anchors | 11/13/2020 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 11/16/2020 | Approved | ANDREW DORSO |
| Footing/Foundation/Slab | 11/16/2020 | Partial Inspection | ANDREW DORSO |
| Reinforced Masonry Frame | 11/20/2020 | Partial Inspection | ANDREW DORSO |
| Reinforced Masonry Frame | 11/30/2020 | Approved | HAMID PISHEHVAR |
| T-Bar Ceiling | 12/2/2020 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 12/14/2020 | Approved | ANDREW DORSO |
| Final | 1/27/2021 | Corrections Issued | ANDREW DORSO |
| Green Building Final | 1/27/2021 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 1/27/2021 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 1/27/2021 | Approved | ANDREW DORSO |
| Final | 8/4/2021 | Permit Finaled | ANDREW DORSO |