6400 N LAUREL CANYON BLVD 91606
Certificate Information: 6400 N LAUREL CANYON BLVD 91606
- Application / Permit
- 19016-20000-33288
- Plan Check / Job No.
- B19VN17868
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- NON-STRUCTURAL INTERIOR REMODEL TO MAKE NEW DOOR OPENING BETWEEN 4TH FLOOR OF (E) OFFICE & ADJACENT (E) PARKING STRUCTURE & REMOVE 1 STANDARD PARKING STALL
- Permit Issued
- Issued on 2/25/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | MARVEL DELACRUZ |
| Corrections Issued | 11/3/2019 | MARVEL DELACRUZ |
| Quality Review Completed | 11/5/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/14/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 11/14/2019 | APPLICANT |
| Applicant returned to address corrections | 2/7/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 2/19/2020 | MARVEL DELACRUZ |
| Issued | 2/25/2020 | LADBS |
| CofO in Progress | 9/1/2020 | ROBERT DAVIS |
| CofO Issued | 9/9/2020 | JEFFREY DURAN |
| Permit Finaled | 9/9/2020 | JEFFREY DURAN |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 1/30/2020 | PABLO ESTRADA |
| DAS Clearance | Cleared | 2/5/2020 | MARVEL DELACRUZ |
Contact Information
| Architect | Diaz,, Osvaldo; Lic. No.: C22020 | 2226 PINECREST COURT FULLERTON, CA 92831 |
| Contractor | Empire Construction; Lic. No.: 973962-B | P O BOX 822 TUSTIN, CA 92781 |
| Engineer | Bryson,, Michael Butler; Lic. No.: S4979 | 285 W 6TH ST 508 SAN PEDRO, CA 90731 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 5/26/2020 | Approved | ROBERT DAVIS |
| Drywall Nailing | 5/29/2020 | Approved | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2020 | Approved | ROBERT DAVIS |
| Final | 6/4/2020 | OK to Issue CofO | ROBERT DAVIS |
| Insulation | 6/4/2020 | Approved | ROBERT DAVIS |
| Smoke Detectors | 6/4/2020 | Approved | ROBERT DAVIS |