5857 N DENNY AVE 91601
Certificate Information: 5857 N DENNY AVE 91601
- Application / Permit
- 19016-20000-33215
- Plan Check / Job No.
- B19VN17809
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 22' X 24' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | JENNIFER LEE |
| Corrections Issued | 10/23/2019 | JENNIFER LEE |
| Plan Check Approved | 12/20/2019 | ANGELICA MARTINEZ |
| Issued | 12/20/2019 | LADBS |
| CofO in Progress | 9/16/2020 | DANIEL ORRANTE |
| Permit Finaled | 9/16/2020 | DANIEL ORRANTE |
| CofO Issued | 9/16/2020 | DANIEL ORRANTE |
| Permit Finaled | 9/16/2020 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2019 | ADRIAN CASTRO |
| Permit | Cleared | 10/23/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/23/2019 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 10/29/2019 | JOHN KIM |
| Construction near power lines | Cleared | 12/14/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/4/2020 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 2/12/2020 | Approved | RAYMOND KEHOE |
| Footing/Foundation/Slab | 2/19/2020 | Approved | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 5/15/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 5/15/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 5/15/2020 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 5/15/2020 | Partial Inspection | WILLIAM KUEHN |
| Interior/Exterior Lathing | 5/20/2020 | Corrections Issued | RAYMOND KEHOE |
| Interior/Exterior Lathing | 5/27/2020 | Partial Approval | RAYMOND KEHOE |
| Drywall Nailing | 6/2/2020 | Approved | THOMAS FINNILA |
| Green Building Rough | 6/2/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 7/14/2020 | Approved | RAYMOND KEHOE |
| Final | 7/14/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| Green Building Final | 7/14/2020 | Approved | RAYMOND KEHOE |
| HVAC-Final | 7/14/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Final | 7/14/2020 | Approved | RAYMOND KEHOE |
| SGSOV-Seismic Gas S/O Valve | 7/14/2020 | SGSOV Approved | RAYMOND KEHOE |
| Smoke Detectors | 7/14/2020 | Approved | RAYMOND KEHOE |
| Final | 9/16/2020 | OK to Issue CofO | DANIEL ORRANTE |