6451 N BOTHWELL ROAD 91335
Certificate Information: 6451 N BOTHWELL ROAD 91335
- Application / Permit
- 19016-20000-32527
- Plan Check / Job No.
- B19VN17451
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE INTO AN ACCESSORY DWELLIING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | ALDOUS CHIC |
| Corrections Issued | 10/10/2019 | ALDOUS CHIC |
| Plan Check Approved | 10/30/2019 | ANGELICA MARTINEZ |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 9/15/2020 | HENRY KIM |
| CofO Issued | 9/16/2020 | JOHN JANSON |
| Permit Finaled | 9/16/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/10/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/10/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | A M C Group Inc; Lic. No.: 749575-B | P O BOX 572110 TARZANA, CA 91357 |
| Engineer | Mirzadeh,, Amir; Lic. No.: C58119 | P O BOX 572110 TARZANA, CA 91357 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/9/2020 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 3/9/2020 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 3/18/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 5/11/2020 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 5/11/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Final | 5/12/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 5/12/2020 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 5/19/2020 | Approved | HENRY KIM |
| Insulation | 5/19/2020 | Partial Approval | HENRY KIM |
| Sewer | 5/19/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Corrections Issued | HENRY KIM |
| Gas Test | 5/28/2020 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 5/28/2020 | Not Ready for Inspection | HENRY KIM |
| Underground Mechanical | 5/28/2020 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 6/3/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2020 | Approved | HENRY KIM |
| Insulation | 6/3/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 6/3/2020 | Approved | HENRY KIM |
| Underground Mechanical | 6/3/2020 | Approved | HENRY KIM |
| Drywall Nailing | 6/17/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 6/17/2020 | Approved | HENRY KIM |
| Shower Pan | 6/18/2020 | Approved | HENRY KIM |
| Green Building Rough | 6/24/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 8/12/2020 | Corrections Issued | HENRY KIM |
| Final | 8/12/2020 | Corrections Issued | HENRY KIM |
| Gas Test | 8/12/2020 | Corrections Issued | HENRY KIM |
| Green Building Final | 8/12/2020 | Approved | HENRY KIM |
| HVAC-Final | 8/12/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 8/12/2020 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 8/12/2020 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 8/12/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 8/28/2020 | Corrections Issued | HENRY KIM |
| Final | 8/28/2020 | Not Ready for Inspection | HENRY KIM |
| Gas Test | 8/28/2020 | Approved | HENRY KIM |
| HVAC-Final | 8/28/2020 | Approved | HENRY KIM |
| PLUMBING-Final | 8/28/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/4/2020 | Approved | HENRY KIM |
| Final | 9/4/2020 | Corrections Issued | HENRY KIM |
| Gas Test | 9/4/2020 | Approved | HENRY KIM |
| Final | 9/15/2020 | OK to Issue CofO | HENRY KIM |