12774 W STAGG ST 91605

Certificate Information: 12774 W STAGG ST 91605

Application / Permit
19016-20000-32517
Plan Check / Job No.
B19VN17439
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-3" X 19'-3" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 2/20/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 JENNIFER LEE
Corrections Issued 10/16/2019 JENNIFER LEE
Building Plans Picked Up 10/17/2019 APPLICANT
Plan Check Approved 2/20/2020 JENNIFER LEE
Issued 2/20/2020 LADBS
CofO in Progress 4/20/2021 GREGG CUMMINGS
Permit Finaled 7/24/2021 MICHAEL SMITH
CofO Issued 7/24/2021 MICHAEL SMITH
Permit Finaled 7/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 12/7/2019 RIDWAN HARDY
Address approval Cleared 2/4/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/4/2020 ADRIAN CASTRO
Permit Cleared 2/4/2020 ADRIAN CASTRO
Sewer availability Cleared 2/4/2020 ADRIAN CASTRO
Trees in Parkway Cleared 2/5/2020 JOHN KIM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/28/2020 Corrections Issued WILLIAM KUEHN
BUILDING-Rough-Frame 3/26/2020 Approved WILLIAM KUEHN
ELECTRICAL-Rough 3/26/2020 Approved WILLIAM KUEHN
Footing/Foundation/Slab 3/26/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 3/26/2020 Partial Inspection WILLIAM KUEHN
Drywall Nailing 3/31/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 3/31/2020 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 3/31/2020 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 3/31/2020 Not Ready for Inspection MISAEL ESPARZA
Insulation 3/31/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/31/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 4/3/2020 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 4/10/2020 Approved WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 4/10/2020 Approved WILLIAM KUEHN
Drywall Nailing 4/20/2020 Approved WILLIAM KUEHN
Green Building Rough 4/20/2020 Approved WILLIAM KUEHN
Final 6/3/2020 Not Ready for Inspection WILLIAM KUEHN
Green Building Final 6/3/2020 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 6/3/2020 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 6/3/2020 Approved WILLIAM KUEHN
Final 4/20/2021 OK to Issue CofO GREGG CUMMINGS