12774 W STAGG ST 91605
Certificate Information: 12774 W STAGG ST 91605
- Application / Permit
- 19016-20000-32517
- Plan Check / Job No.
- B19VN17439
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-3" X 19'-3" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | JENNIFER LEE |
| Corrections Issued | 10/16/2019 | JENNIFER LEE |
| Building Plans Picked Up | 10/17/2019 | APPLICANT |
| Plan Check Approved | 2/20/2020 | JENNIFER LEE |
| Issued | 2/20/2020 | LADBS |
| CofO in Progress | 4/20/2021 | GREGG CUMMINGS |
| Permit Finaled | 7/24/2021 | MICHAEL SMITH |
| CofO Issued | 7/24/2021 | MICHAEL SMITH |
| Permit Finaled | 7/24/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/7/2019 | RIDWAN HARDY |
| Address approval | Cleared | 2/4/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | ADRIAN CASTRO |
| Permit | Cleared | 2/4/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/4/2020 | ADRIAN CASTRO |
| Trees in Parkway | Cleared | 2/5/2020 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/28/2020 | Corrections Issued | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 3/26/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 3/26/2020 | Approved | WILLIAM KUEHN |
| Footing/Foundation/Slab | 3/26/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 3/26/2020 | Partial Inspection | WILLIAM KUEHN |
| Drywall Nailing | 3/31/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/31/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 3/31/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 3/31/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 3/31/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 3/31/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/3/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 4/10/2020 | Approved | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 4/10/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 4/20/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 4/20/2020 | Approved | WILLIAM KUEHN |
| Final | 6/3/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Final | 6/3/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2020 | SGSOV Approved | WILLIAM KUEHN |
| Smoke Detectors | 6/3/2020 | Approved | WILLIAM KUEHN |
| Final | 4/20/2021 | OK to Issue CofO | GREGG CUMMINGS |