5527 N COSTELLO AVE 91401
Certificate Information: 5527 N COSTELLO AVE 91401
- Application / Permit
- 19016-20000-32293
- Plan Check / Job No.
- B19VN17290
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE W/STORAGE INTO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 2/25/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2019 | HAYATO TSUCHIYA |
| Corrections Issued | 10/10/2019 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/15/2019 | APPLICANT |
| Applicant returned to address corrections | 1/28/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 2/18/2020 | HAYATO TSUCHIYA |
| Issued | 2/25/2020 | LADBS |
| CofO in Progress | 7/7/2022 | RICHARD DOCKUS |
| Permit Finaled | 7/14/2022 | MICHAEL SMITH |
| CofO Issued | 7/14/2022 | MICHAEL SMITH |
| Permit Finaled | 7/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/24/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | JOHN LIN |
Contact Information
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
| Engineer | Keshishian,, Nejdeh; Lic. No.: C38341 | 2654 RISA DR GLENDALE, CA 91208 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2021 | Approved | RICHARD DOCKUS |
| Sewer | 11/17/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 1/11/2022 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 1/11/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 1/18/2022 | Corrections Issued | RICHARD DOCKUS |
| Sewer | 1/18/2022 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 1/21/2022 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 1/26/2022 | Corrections Issued | ALAN MORELOS |
| Underground Mechanical | 2/3/2022 | Corrections Issued | RICHARD DOCKUS |
| Underground Mechanical | 2/7/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/11/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 3/11/2022 | Approved | JOHN HAYES |
| Green Building Rough | 3/11/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 3/11/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/11/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/17/2022 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 3/17/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Partial Approval | ALAN MORELOS |
| Gas Test | 3/17/2022 | Partial Approval | ALAN MORELOS |
| HVAC-Rough | 3/17/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 3/17/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 3/23/2022 | No Access for Inspection | RAUL OLAGI |
| Green Building Rough | 3/23/2022 | No Access for Inspection | RAUL OLAGI |
| HVAC-Rough | 3/23/2022 | No Access for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 3/23/2022 | No Access for Inspection | RAUL OLAGI |
| HVAC-Rough | 3/30/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/30/2022 | Corrections Issued | ALAN MORELOS |
| BUILDING-Rough-Frame | 4/6/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Rough | 4/6/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 4/6/2022 | Approved | ALAN MORELOS |
| Insulation | 4/8/2022 | Conditional Approval | RAUL OLAGI |
| Special/Order Compliance | 4/8/2022 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 4/8/2022 | Partial Inspection | ALAN MORELOS |
| Drywall Nailing | 4/15/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 4/15/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Drywall Nailing | 4/20/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 4/20/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/17/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/17/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 6/17/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 6/17/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 6/17/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Final | 6/17/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 6/17/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/27/2022 | Approved | RICHARD DOCKUS |
| Final | 6/27/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Final | 6/27/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 6/27/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/27/2022 | SGSOV Approved | RICHARD DOCKUS |
| Final | 7/5/2022 | OK to Issue CofO | RICHARD DOCKUS |