7719-7721 N HATTON PL 91335

Certificate Information: 7719-7721 N HATTON PL 91335

Application / Permit
19016-20000-32227
Plan Check / Job No.
B19VN17252
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 10/30/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2019 APPLICANT
Assigned to Plan Check Engineer 10/8/2019 SELLA BENYAMIN
Corrections Issued 10/9/2019 SELLA BENYAMIN
Building Plans Picked Up 10/16/2019 APPLICANT
Plan Check Approved 10/23/2019 SELLA BENYAMIN
Issued 10/30/2019 LADBS
CofO in Progress 6/18/2020 VINCENT HANLEY
CofO Issued 6/25/2020 DONALD SUNSERI
Permit Finaled 6/25/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 10/16/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 10/16/2019 DYNL MIRANDA
Sewer availability Cleared 10/16/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Ochoa Victor Manuel; Lic. No.: 908306-B 13700 FOOTHILL BLVD #920151      SYLMAR, CA 91342

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/9/2019 Approved DAVID SANDOVAL
Footing/Foundation/Slab 12/11/2019 Approved DAVID SANDOVAL
Sewer 12/11/2019 Approved DAVID SANDOVAL
Underground Mechanical 12/11/2019 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 2/10/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 2/10/2020 Corrections Issued KATHRYN BUTTERWORTH
Green Building Rough 2/10/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 2/10/2020 Corrections Issued KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 2/20/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 2/20/2020 Approved VINCENT HANLEY
Green Building Rough 2/20/2020 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 2/20/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 2/20/2020 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 3/5/2020 Approved VINCENT HANLEY
Green Building Rough 3/5/2020 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 3/5/2020 Approved VINCENT HANLEY
PLUMBING-Rough 3/5/2020 Approved VINCENT HANLEY
Insulation 3/10/2020 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 3/10/2020 Partial Approval VINCENT HANLEY
Drywall Nailing 3/13/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/18/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/24/2020 Approved VINCENT HANLEY
Final 4/24/2020 Corrections Issued VINCENT HANLEY
Green Building Final 4/24/2020 Approved VINCENT HANLEY
Green Building Rough 4/24/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/24/2020 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 4/24/2020 Approved VINCENT HANLEY
Final 5/27/2020 Not Ready for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/27/2020 SGSOV Not Ready VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/4/2020 SGSOV Not Ready VINCENT HANLEY
ELECTRICAL-Final 6/5/2020 Corrections Issued VINCENT HANLEY
Pre-Inspection 6/5/2020 Corrections Issued VINCENT HANLEY
Final 6/12/2020 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/12/2020 SGSOV Approved JEFFREY PARD
ELECTRICAL-Final 6/15/2020 Not Ready for Inspection DAVID SCANTLIN
Final 6/15/2020 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Final 6/17/2020 Approved VINCENT HANLEY
Final 6/17/2020 OK to Issue CofO VINCENT HANLEY
HVAC-Final 6/17/2020 Approved VINCENT HANLEY
PLUMBING-Final 6/17/2020 Approved VINCENT HANLEY