281 N BENTLEY CIR 90049
Certificate Information: 281 N BENTLEY CIR 90049
- Application / Permit
- 19016-20000-32199
- Plan Check / Job No.
- B19VN17234
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND BASEMENT
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/4/2021
Permit Application Status History
| Submitted | 10/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | SELLA BENYAMIN |
| Corrections Issued | 10/21/2019 | SELLA BENYAMIN |
| Quality Review Completed | 10/22/2019 | STEVEN KIM |
| Building Plans Picked Up | 10/25/2019 | APPLICANT |
| Plan Check Approved | 11/22/2019 | SELLA BENYAMIN |
| Issued | 1/27/2020 | LADBS |
| Permit Finaled | 3/4/2021 | CARLOS MATAMOROS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2019 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 11/7/2019 | BARTON HOLMES |
| Sewer availability | Cleared | 11/7/2019 | GUILLERMO PETRA |
Contact Information
| Architect | Yotnegparian,, Alain Levon; Lic. No.: C26374 | 11541 DONA PEPITA PLACE STUDIO CITY, CA 91604 |
| Contractor | Ciccone Builders Inc; Lic. No.: 850466-B | 3826 GRANDVIEW BLVD #66011 LOS ANGELES, CA 90066 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2020 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/1/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/1/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/1/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 4/10/2020 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 4/10/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 4/10/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 4/16/2020 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/23/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 4/23/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 5/4/2020 | Partial Approval | ANTHONY MCDOWALL |
| PLUMBING-Rough | 5/7/2020 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 6/3/2020 | Corrections Issued | CARLOS MATAMOROS |
| Structural Steel Frame | 6/3/2020 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Steel/Welding | 7/7/2020 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/5/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/5/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 8/5/2020 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/5/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/7/2020 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/7/2020 | Partial Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/13/2020 | Approved | CARLOS MATAMOROS |
| Shower Pan | 8/13/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 10/16/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 10/16/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/28/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 10/28/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/28/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 12/30/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 2/24/2021 | Approved | CARLOS MATAMOROS |
| Final | 3/4/2021 | Permit Finaled | CARLOS MATAMOROS |
| Gas Test | 3/4/2021 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 3/4/2021 | Approved | CARLOS MATAMOROS |