13366 W SUNBURST ST 91331

Certificate Information: 13366 W SUNBURST ST 91331

Application / Permit
19016-20000-32179
Plan Check / Job No.
B19VN17222
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 2- CAR GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. PER LA STD WFPP.
Permit Issued
Issued on 12/9/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2019 APPLICANT
Assigned to Plan Check Engineer 10/8/2019 ALDOUS CHIC
Corrections Issued 10/8/2019 ALDOUS CHIC
Applicant returned to address corrections 10/10/2019 ANGELICA DAVE
Plan Check Approved 10/17/2019 TROY DEGUZMAN
Issued 12/9/2019 LADBS
CofO in Progress 6/23/2020 MICHEL ABAJAN
Permit Finaled 7/20/2020 MICHAEL SMITH
CofO Issued 7/20/2020 MICHAEL SMITH
Permit Finaled 7/20/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/8/2019 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 10/8/2019 SAFA JAVANMARDI
Sewer availability Cleared 10/8/2019 SAFA JAVANMARDI
Permit Cleared 10/10/2019 GUILLERMO PETRA

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B 13302 FILMORE ST      PACOIMA, CA 91331

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/30/2019 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 1/2/2020 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 1/15/2020 Approved MICHEL ABAJAN
Footing/Foundation/Slab 1/15/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 1/15/2020 Approved MICHEL ABAJAN
Wood Frame 1/15/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/23/2020 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 1/23/2020 Approved MICHEL ABAJAN
Insulation 1/24/2020 Approved MICHEL ABAJAN
Drywall Nailing 1/28/2020 Approved MICHEL ABAJAN
Underground Mechanical 2/13/2020 Not Ready for Inspection MICHEL ABAJAN
Underground Mechanical 2/18/2020 Partial Approval MICHEL ABAJAN
Underground Mechanical 2/25/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 3/20/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/20/2020 Approved MICHEL ABAJAN
Final 3/20/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 3/20/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 3/20/2020 Approved MICHEL ABAJAN
HVAC-Final 3/20/2020 Approved MICHEL ABAJAN
MERV13>=Final 3/20/2020 Approved MICHEL ABAJAN
MERV13>=Rough 3/20/2020 Approved MICHEL ABAJAN
PLUMBING-Final 3/20/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/20/2020 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 3/20/2020 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 3/20/2020 Approved MICHEL ABAJAN
Final 3/24/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 3/24/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/24/2020 SGSOV Not Ready MICHEL ABAJAN
Final 6/10/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 6/10/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/10/2020 SGSOV Approved MICHEL ABAJAN
Final 6/23/2020 OK to Issue CofO MICHEL ABAJAN