333 N ARDEN BLVD 90004

Certificate Information: 333 N ARDEN BLVD 90004

Application / Permit
19016-20000-32149
Plan Check / Job No.
B19VN17209
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIY PER AB 494 AND SB 229 . ---- Comply with department order effective date 10/8/2018, permit will expire 30 days from issuance date ---
Permit Issued
Issued on 3/20/2020
Issuing Office
Metro
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2019 APPLICANT
Assigned to Plan Check Engineer 10/8/2019 ALDOUS CHIC
Corrections Issued 10/8/2019 ALDOUS CHIC
Refund in Progress 11/18/2019 SELENIA GARCIA
Plan Check Approved 3/11/2020 ANGELICA MARTINEZ
Issued 3/20/2020 LADBS
CofO in Progress 7/17/2024 COREY HUPP
CofO Issued 8/6/2024 DANIEL SANCHEZ
Permit Finaled 8/6/2024 DANIEL SANCHEZ

Permit Application Clearance Information

Construction near power lines Cleared 12/8/2019 RIDWAN HARDY
Address approval Cleared 2/18/2020 ERIK BEASLEY
Sewer availability Cleared 2/18/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/11/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/8/2020 Approved EDDY ARDESSI
Footing/Foundation/Slab 8/5/2020 Corrections Issued GORDON ZUBER
Masonry Wall/Backfill 8/5/2020 Not Ready for Inspection GORDON ZUBER
Deputy Drilled-In Anchors 6/11/2021 Conditional Approval GABRIEL HERRERA
Excavation/Setback/Form/Re-Bar 6/11/2021 Not Ready for Inspection GORDON ZUBER
Excavation/Setback/Form/Re-Bar 6/14/2021 No Access for Inspection GORDON ZUBER
Wood Frame 6/14/2021 No Access for Inspection GORDON ZUBER
Excavation/Setback/Form/Re-Bar 6/15/2021 Approved GORDON ZUBER
Wood Frame 6/15/2021 Not Ready for Inspection GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 6/18/2021 Not Ready for Inspection JOEL WILLIAMS
Wood Frame 6/18/2021 Partial Approval JOEL WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Approved JOEL WILLIAMS
Interior/Exterior Lathing 8/4/2021 No Access for Inspection ZEYDI STEWART
Interior/Exterior Lathing 8/5/2021 Corrections Issued ZEYDI STEWART
Interior/Exterior Lathing 8/31/2021 Partial Approval ZEYDI STEWART
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Approved ZEYDI STEWART
Footing/Foundation/Slab 10/6/2021 Approved ZEYDI STEWART
Green Building Rough 10/6/2021 Not Ready for Inspection ZEYDI STEWART
Interior/Exterior Lathing 10/6/2021 Approved ZEYDI STEWART
BUILDING-Rough-Frame 11/15/2021 Not Ready for Inspection ZEYDI STEWART
ELECTRICAL-Rough 11/15/2021 Corrections Issued ZEYDI STEWART
Final 11/15/2021 Not Ready for Inspection ZEYDI STEWART
Green Building Final 11/15/2021 Not Ready for Inspection ZEYDI STEWART
Green Building Rough 11/15/2021 Not Ready for Inspection ZEYDI STEWART
HVAC-Final 11/15/2021 Not Ready for Inspection ZEYDI STEWART
HVAC-Rough 11/15/2021 Corrections Issued ZEYDI STEWART
METHANE-Final 11/15/2021 Not Ready for Inspection ZEYDI STEWART
METHANE-Rough 11/15/2021 Not Ready for Inspection ZEYDI STEWART
PLUMBING-Rough 11/15/2021 Corrections Issued ZEYDI STEWART
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Not Ready ZEYDI STEWART
Smoke Detectors 11/15/2021 Not Ready for Inspection ZEYDI STEWART
Pre-Inspection 1/18/2022 No Access for Inspection ZEYDI STEWART
BUILDING-Rough-Frame 1/25/2022 Corrections Issued ZEYDI STEWART
Final 1/25/2022 Not Ready for Inspection ZEYDI STEWART
Green Building Final 1/25/2022 Corrections Issued ZEYDI STEWART
Green Building Rough 1/25/2022 Not Ready for Inspection ZEYDI STEWART
METHANE-Final 1/25/2022 Not Ready for Inspection ZEYDI STEWART
METHANE-Rough 1/25/2022 Corrections Issued ZEYDI STEWART
SGSOV-Seismic Gas S/O Valve 1/25/2022 SGSOV Not Required ZEYDI STEWART
Smoke Detectors 1/25/2022 Corrections Issued ZEYDI STEWART
Special/Order Compliance 1/25/2022 Partial Inspection PIERRE VEGA
Deck 4/1/2022 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 4/1/2022 Corrections Issued COREY HUPP
HVAC-Rough 4/1/2022 Approved COREY HUPP
Sewer 4/1/2022 Not Ready for Inspection COREY HUPP
Smoke Detectors 4/1/2022 Approved COREY HUPP
BUILDING-Rough-Frame 7/16/2024 Approved COREY HUPP
Final 7/16/2024 OK to Issue CofO COREY HUPP
Green Building Final 7/16/2024 Approved COREY HUPP
Green Building Rough 7/16/2024 Approved COREY HUPP
METHANE-Final 7/16/2024 Approved COREY HUPP
METHANE-Rough 7/16/2024 Approved COREY HUPP