136 1/2 E 54TH ST 90011
Certificate Information: 136 1/2 E 54TH ST 90011
- Application / Permit
- 19016-20000-32127
- Plan Check / Job No.
- B19VN17205
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert downstairs garage to storage; add 2-stories 14'4" x 12' and convert to accessory dwelling unit per AB4945 & SB229. All works are per design.
- Permit Issued
- Issued on 12/16/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/27/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | ALDOUS CHIC |
| Corrections Issued | 10/21/2019 | ALDOUS CHIC |
| Quality Review Completed | 10/22/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 10/23/2019 | APPLICANT |
| Applicant returned to address corrections | 11/25/2019 | ALDOUS CHIC |
| Plan Check Approved | 12/11/2019 | ALDOUS CHIC |
| Issued | 12/16/2019 | LADBS |
| CofO in Progress | 7/17/2020 | ENRIQUE MIRELES |
| Permit Finaled | 9/27/2020 | DEROLD HAUFF |
| CofO Issued | 9/27/2020 | DEROLD HAUFF |
| Permit Finaled | 9/27/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2019 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/5/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2019 | PAMELA TENEZA |
| Housing rent stabilization | Cleared | 12/6/2019 | MICHAEL GREGERSON |
| ZI | Cleared | 12/9/2019 | RICHARD REASER |
| Green Code | Cleared | 12/10/2019 | MICHAEL AYERS |
Contact Information
| Contractor | C C D L Investments Inc; Lic. No.: 906858-B | 205 AVENIDA DEL MAR #0896 SAN CLEMENTE, CA 92672 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/9/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 1/9/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 1/9/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 1/9/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/9/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 1/28/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 1/28/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 1/28/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 1/28/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/28/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/24/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 2/24/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/24/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Drywall Nailing | 3/3/2020 | No Access for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 3/3/2020 | No Access for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 3/3/2020 | No Access for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 3/5/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/16/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 3/16/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 3/16/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 4/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 4/17/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/17/2020 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 4/21/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/6/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/6/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/6/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/6/2020 | No Access for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 5/8/2020 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 5/8/2020 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 5/8/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/12/2020 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 5/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 5/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 5/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/29/2020 | No Access for Inspection | RUBEN SALAS |
| Final | 5/29/2020 | No Access for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 5/29/2020 | No Access for Inspection | RUBEN SALAS |
| Green Building Final | 5/29/2020 | No Access for Inspection | RUBEN SALAS |
| PLUMBING-Final | 5/29/2020 | No Access for Inspection | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 5/29/2020 | SGSOV Not Ready | RUBEN SALAS |
| Smoke Detectors | 5/29/2020 | No Access for Inspection | RUBEN SALAS |
| ELECTRICAL-Final | 6/2/2020 | Approved | FREDDIE RIVERA |
| Final | 6/2/2020 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 6/2/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 6/8/2020 | Approved | ENRIQUE MIRELES |
| Final | 6/8/2020 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/8/2020 | Approved | ENRIQUE MIRELES |
| Green Building Final | 6/8/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 6/8/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/8/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/8/2020 | Approved | ENRIQUE MIRELES |
| Final | 7/17/2020 | OK to Issue CofO | ENRIQUE MIRELES |