8768 N CORBIN AVE 91324

Certificate Information: 8768 N CORBIN AVE 91324

Application / Permit
19016-20000-32113
Plan Check / Job No.
B19VN17194
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Dance Studio or Academy
Work Description
CONVERT 60' x 85'2.5" (E) RETAIL STORE TO PRIVATE CLUB REHEARSAL (B-OCC) VENUE FOR MEMBERS ONLY FOR THE PERFORMING ARTS.
Permit Issued
Issued on 11/18/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2019 APPLICANT
Assigned to Plan Check Engineer 10/7/2019 GURUNATH NESARAJAH
Corrections Issued 10/7/2019 GURUNATH NESARAJAH
Plan Check Approved 11/15/2019 LUIS RINCON
Issued 11/18/2019 LADBS
CofO in Progress 2/7/2020 JEFFREY FULTON
CofO in Progress 2/11/2020 JEFFREY FULTON
CofO Issued 2/20/2020 JAMES STEPHENS
Permit Finaled 2/20/2020 JAMES STEPHENS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/23/2019 GUILLERMO PETRA
Sewer availability Cleared 10/23/2019 GUILLERMO PETRA
ZA Case Cleared 10/23/2019 STEVEN WECHSLER
ZA Case Cleared 10/23/2019 STEVEN WECHSLER
ZA Case Cleared 10/23/2019 STEVEN WECHSLER
ZA Case Cleared 10/23/2019 STEVEN WECHSLER
ZA Case Cleared 10/23/2019 STEVEN WECHSLER

Contact Information

Contractor Four Point Design Build Inc; Lic. No.: 982460-B 23722 FITZGERALD STREET      WEST HILLS, CA 91304
Engineer Kardjian,, Vahe Matios; Lic. No.: C40821 1648 W GLENOAKS BLVD STE 102      GLENDALE, CA 91201

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/13/2019 Partial Approval MILLARD ARDOIN
Wood Frame 12/13/2019 Partial Approval MILLARD ARDOIN
Drywall Nailing 12/16/2019 Partial Approval MILLARD ARDOIN
Wood Frame 12/18/2019 Approved MILLARD ARDOIN
Wood Frame 1/2/2020 Partial Inspection JEFFREY FULTON
Partition/T-Bar Ceiling 1/14/2020 Partial Inspection JEFFREY FULTON
Final 1/31/2020 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 1/31/2020 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 1/31/2020 Approved JEFFREY FULTON
Final 2/6/2020 Conditional Approval JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 2/6/2020 SGSOV No Gas JEFFREY FULTON
Final 2/11/2020 OK to Issue CofO JEFFREY FULTON