9710 S HAAS AVE 90047
Certificate Information: 9710 S HAAS AVE 90047
- Application / Permit
- 19016-20000-32088
- Plan Check / Job No.
- B19VN17180
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER DESIGN.
- Permit Issued
- Issued on 1/28/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/15/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2019 | JENNIFER LEE |
| Corrections Issued | 10/8/2019 | JENNIFER LEE |
| Building Plans Picked Up | 10/10/2019 | APPLICANT |
| Plan Check Approved | 11/27/2019 | JENNIFER LEE |
| Issued | 1/28/2020 | LADBS |
| CofO in Progress | 7/23/2020 | JOSEPH MCGARRY |
| Permit Finaled | 8/15/2020 | DEROLD HAUFF |
| CofO Issued | 8/15/2020 | DEROLD HAUFF |
| Permit Finaled | 8/15/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/10/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/10/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 11/22/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/22/2019 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Myrick Charles S; Lic. No.: 849976-B | 1312 HIGHLAND AVE DUARTE, CA 91010 |
Inspector Information
| RAUL BARAJAS, (213) 202-3211 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/17/2020 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 3/17/2020 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 3/17/2020 | Corrections Issued | HORACE FULTZ |
| Gas Test | 3/17/2020 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Rough | 3/17/2020 | Approved | HORACE FULTZ |
| METHANE-Rough | 3/17/2020 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 3/17/2020 | Corrections Issued | HORACE FULTZ |
| ELECTRICAL-Rough | 3/23/2020 | Partial Approval | HORACE FULTZ |
| Footing/Foundation/Slab | 3/23/2020 | Not Ready for Inspection | HORACE FULTZ |
| Gas Test | 3/23/2020 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 3/23/2020 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 4/3/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 4/3/2020 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/3/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/3/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/3/2020 | Approved | FREDDIE RIVERA |
| Final | 6/22/2020 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 6/22/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/22/2020 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 6/22/2020 | Corrections Issued | FREDDIE RIVERA |
| Final | 7/23/2020 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 7/23/2020 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 7/23/2020 | Approved | JOSEPH MCGARRY |