6640 N WOODLEY AVE 91406

Certificate Information: 6640 N WOODLEY AVE 91406

Application / Permit
19016-20000-32067
Plan Check / Job No.
B19VN17173
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
REMODEL TO (E) TWO STORY 34 UNITS APARTMENT: CONVERT (6) STUDIO UNITS TO 1-BED, (8) 1- BED UNITS TO 2- BED, (1) 1-BED UNITS TO 3-BED, (2) 2-BED TO 3- BED, CONVERT (E) 564SF GARAGE/STORAGE FOR BEDRM EXTENSION, AND RESTRIPE PARKING FOR SITE.
Permit Issued
Issued on 12/19/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2019 APPLICANT
Green Plans Picked Up 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 DAWN MC NULTY
Disabled Access Plans Picked Up 10/18/2019 APPLICANT
Corrections Issued 10/21/2019 DAWN MC NULTY
Quality Review Completed 10/22/2019 CHON CHIO KUO
Building Plans Picked Up 10/29/2019 APPLICANT
Plan Check Approved 12/11/2019 DAWN MC NULTY
Issued 12/19/2019 LADBS
CofO in Progress 5/4/2021 CAMERON CHABAN
Permit Finaled 5/10/2021 JEFFREY DURAN
CofO Issued 5/10/2021 JEFFREY DURAN
Permit Finaled 5/10/2021 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 11/1/2019 NOAH MCCOY
CPC Cleared 11/1/2019 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 11/1/2019 THOMAS LANG
Sewer availability Cleared 11/1/2019 THOMAS LANG
ZA Case Cleared 11/1/2019 NOAH MCCOY
ZI Cleared 11/1/2019 NOAH MCCOY
Green Code Cleared 11/7/2019 DAVID MATSON
DAS Clearance Cleared 11/12/2019 DAWN MC NULTY
Fire Marshall Fire Life Safety Cleared 11/15/2019 VIDAL GARCIA
Miscellaneous Cleared 12/16/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor Stay Forever Construction Corporation; Lic. No.: 986055-B 27138 CHERRY LAUREL PL      CANYON COUNTRY, CA 91387

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/30/2020 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 5/22/2020 Approved HAMID PISHEHVAR
Deputy Wood Construction 7/9/2020 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Approved ANDREW DORSO
Interior/Exterior Lathing 7/21/2020 Approved ANDREW DORSO
Green Building Rough 8/24/2020 Approved ANDREW DORSO
Insulation 8/24/2020 Approved ANDREW DORSO
Wood Frame 8/24/2020 Partial Inspection ANDREW DORSO
Drywall Nailing 8/31/2020 Approved HAMID PISHEHVAR
Interior/Exterior Lathing 8/31/2020 Approved HAMID PISHEHVAR
Interior/Exterior Lathing 9/3/2020 Approved HAMID PISHEHVAR
Drywall Nailing 9/8/2020 Partial Approval JOHN DODGE
Interior/Exterior Lathing 9/8/2020 Partial Approval JOHN DODGE
Drywall Nailing 3/12/2021 Approved CAMERON CHABAN
Final 3/12/2021 Partial Inspection CAMERON CHABAN
Green Building Final 3/12/2021 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Approved CAMERON CHABAN
Smoke Detectors 3/12/2021 Approved CAMERON CHABAN
Wood Frame 3/12/2021 Approved CAMERON CHABAN
Final 3/17/2021 Partial Inspection CAMERON CHABAN
Green Building Final 3/17/2021 Approved CAMERON CHABAN
Final 3/23/2021 Partial Inspection CAMERON CHABAN
Final 3/24/2021 OK to Issue CofO CAMERON CHABAN