12080 W VENTURA PL 91604
Certificate Information: 12080 W VENTURA PL 91604
- Application / Permit
- 19016-20000-32033
- Plan Check / Job No.
- B19VN17156
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ADD FACADE AND REMODEL (E) STAIRWAY, ADD MOMENT FRAME, FOR CORE & SHELL ONLY..NO CHANGE ON (E) TENANT SPACE & AREA.
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | CHON CHIO KUO |
| Corrections Issued | 10/21/2019 | CHON CHIO KUO |
| Quality Review Completed | 10/23/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/7/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 11/7/2019 | APPLICANT |
| Green Plans Picked Up | 11/7/2019 | APPLICANT |
| Applicant returned to address corrections | 1/22/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 1/23/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 2/12/2020 | CHON CHIO KUO |
| Plan Check Approved | 2/21/2020 | CHON CHIO KUO |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 2/1/2021 | ROBERT DAVIS |
| Permit Finaled | 3/17/2021 | JEFFREY DURAN |
| CofO Issued | 3/17/2021 | JEFFREY DURAN |
| Permit Finaled | 3/17/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/8/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/8/2019 | LEE GUILBEAUX |
| ZA Case | Cleared | 11/8/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 11/8/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 11/8/2019 | HERMINIGILDO AGUSTIN |
| Green Code | Cleared | 12/30/2019 | AARON COSTA |
| Comm Cor/Mini-Mall | Cleared | 1/23/2020 | STEVEN WECHSLER |
| Comm Cor/Mini-Mall | Cleared | 1/23/2020 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2020 | JOHN TRIANTAFYLLOS |
| Specific Plan | Cleared | 1/23/2020 | STEVEN WECHSLER |
| ZA Case | Cleared | 1/23/2020 | STEVEN WECHSLER |
| DAS Clearance | Cleared | 2/21/2020 | CHON CHIO KUO |
Contact Information
| Architect | Rocha,, Carlos Joel; Lic. No.: C19775 | 28025 DOROTHY DRIVE SUITE 206 AGOURA HILLS, CA 91301 |
| Contractor | Rocha Nuez Abdoh Construction Inc; Lic. No.: 791474-B | 28025 DOROTHY DRIVE #100 AGOURA HILLS, CA 91301 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 5/21/2020 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2020 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 5/22/2020 | Conditional Approval | ROBERT DAVIS |
| Green Building Rough | 7/6/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 7/6/2020 | Partial Approval | ROBERT DAVIS |
| Interior/Exterior Lathing | 7/27/2020 | Partial Approval | ROBERT DAVIS |
| Interior/Exterior Lathing | 8/28/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 9/4/2020 | Conditional Approval | ROBERT DAVIS |
| Final | 11/18/2020 | Corrections Issued | ROBERT DAVIS |
| Green Building Final | 11/18/2020 | Approved | ROBERT DAVIS |
| Green Building Rough | 11/18/2020 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 11/18/2020 | Approved | ROBERT DAVIS |
| Wood Frame | 11/18/2020 | Approved | ROBERT DAVIS |
| Final | 2/1/2021 | OK to Issue CofO | ROBERT DAVIS |