953 S WESTCHESTER PL 90019

Certificate Information: 953 S WESTCHESTER PL 90019

Application / Permit
19016-20000-31575
Plan Check / Job No.
B19VN16927
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT IRREGULAR SHAPE 29'9" X 30'9" (490 SF ) PORTION OF DETACHED GARAGE TO ACCESORY DWELLING UNIT PER AB 494 AND SB 229, All works are per design ---------------Comply with department order effective date 6/19/2013, permit will expire 30 days from issuance date
Permit Issued
Issued on 1/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 ALDOUS CHIC
Corrections Issued 10/3/2019 ALDOUS CHIC
Plan Check Approved 12/13/2019 ALDOUS CHIC
Issued 1/13/2020 LADBS
CofO in Progress 4/28/2021 GORDON ZUBER
Permit Finaled 5/6/2021 DANIEL SANCHEZ
CofO Issued 5/6/2021 DANIEL SANCHEZ
Permit Finaled 5/6/2021 DANIEL SANCHEZ

Permit Application Clearance Information

Construction near power lines Cleared 12/4/2019 RIDWAN HARDY
Construction near power lines Cleared 12/4/2019 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 12/12/2019 THOMAS LANG
Sewer availability Cleared 12/12/2019 THOMAS LANG
Address approval Cleared 12/13/2019 APEKSHYA BAJRACHARYA
HPOZ Cleared 12/13/2019 HERMINIGILDO AGUSTIN

Contact Information

Contractor Don Construction; Lic. No.: 840108-B 28063 MEMORY LN      VALENCIA, CA 91354
Engineer Kim,, Taewon; Lic. No.: C80632 28000 S WESTERN AVE UNIT 209      SAN PEDRO, CA 90732

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/17/2020 Conditional Approval BENEDICT MATHIAS
Deputy Other (see comments) 1/17/2020 Conditional Approval BENEDICT MATHIAS
BUILDING-Rough-Frame 1/22/2020 Not Ready for Inspection BENEDICT MATHIAS
ELECTRICAL-Rough 1/22/2020 Not Ready for Inspection BENEDICT MATHIAS
Green Building Rough 1/22/2020 Not Ready for Inspection BENEDICT MATHIAS
PLUMBING-Rough 1/22/2020 Not Ready for Inspection BENEDICT MATHIAS
Wood Frame 1/22/2020 Not Ready for Inspection BENEDICT MATHIAS
Deputy Drilled-In Anchors 2/5/2020 Approved BENEDICT MATHIAS
BUILDING-Rough-Frame 2/10/2020 Approved BENEDICT MATHIAS
ELECTRICAL-Rough 2/10/2020 Corrections Issued BENEDICT MATHIAS
Footing/Foundation/Slab 2/10/2020 Approved BENEDICT MATHIAS
Gas Test 2/10/2020 Approved BENEDICT MATHIAS
Green Building Rough 2/10/2020 Approved BENEDICT MATHIAS
Insulation 2/10/2020 Approved BENEDICT MATHIAS
Interior/Exterior Lathing 2/10/2020 Approved BENEDICT MATHIAS
PLUMBING-Rough 2/10/2020 Corrections Issued BENEDICT MATHIAS
Drywall Nailing 2/13/2020 Approved BENEDICT MATHIAS
PLUMBING-Rough 2/18/2020 Approved EDDY ARDESSI
Sewer 2/18/2020 Approved EDDY ARDESSI
Final 3/10/2020 Corrections Issued EDDY ARDESSI
Green Building Final 3/10/2020 Approved EDDY ARDESSI
SGSOV-Seismic Gas S/O Valve 3/10/2020 SGSOV Not Ready EDDY ARDESSI
Smoke Detectors 3/10/2020 Approved EDDY ARDESSI
Final 4/14/2020 Corrections Issued GORDON ZUBER
SGSOV-Seismic Gas S/O Valve 4/14/2020 SGSOV Approved GORDON ZUBER
Final 4/27/2021 Conditional Approval GORDON ZUBER