11686 W SHELDON ST 91352
Certificate Information: 11686 W SHELDON ST 91352
- Application / Permit
- 19016-20000-31331
- Plan Check / Job No.
- B19VN16810
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- DEMO PORTION OF 1ST (18'-10" X 5'-7") & 2ND (20' X 5'-7") TO (E) 2-STORY OFFICE; INTERIOR REMODEL
- Permit Issued
- Issued on 1/7/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 10/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/15/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/15/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/16/2019 | APPLICANT |
| Applicant returned to address corrections | 11/22/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/31/2019 | NILOOFAR MEHRAIN |
| Issued | 1/7/2020 | LADBS |
| CofO in Progress | 5/19/2025 | ANDREW DORSO |
| Permit Finaled | 5/19/2025 | JEFFREY DURAN |
| CofO Issued | 5/19/2025 | JEFFREY DURAN |
| Permit Finaled | 5/19/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 10/16/2019 | DAISY BENICIA |
| Roof/Waste drainage to street | Cleared | 11/22/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 11/22/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | JOHN LIN |
| DAS Clearance | Cleared | 12/16/2019 | NORLITO MEDRANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/29/2020 | Partial Approval | DANNY RODRIGUEZ |
| Wood Frame | 11/9/2020 | Corrections Issued | ANDREW DORSO |
| Interior/Exterior Lathing | 11/30/2020 | Approved | HAMID PISHEHVAR |
| Insulation | 4/19/2021 | Approved | ROBERT DAVIS |
| Drywall Nailing | 5/12/2021 | Approved | ANDREW DORSO |
| Final | 4/30/2025 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV No Gas | ANDREW DORSO |
| Smoke Detectors | 4/30/2025 | Approved | ANDREW DORSO |
| Wood Frame | 4/30/2025 | Not Ready for Inspection | ANDREW DORSO |
| Final | 5/14/2025 | OK to Issue CofO | ANDREW DORSO |
| Wood Frame | 5/14/2025 | Approved | ANDREW DORSO |