124 S NORTON AVE 90004

Certificate Information: 124 S NORTON AVE 90004

Application / Permit
19016-20000-30919
Plan Check / Job No.
B19VN16611
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'-3" X 20'-7" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/27/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2019 APPLICANT
Assigned to Plan Check Engineer 9/30/2019 RAPHAEL ROSAS
Corrections Issued 9/30/2019 RAPHAEL ROSAS
Building Plans Picked Up 10/1/2019 APPLICANT
Plan Check Approved 2/4/2020 RAPHAEL ROSAS
Issued 2/11/2020 LADBS
CofO in Progress 9/14/2020 CHRIS CHRISTENSEN
Permit Finaled 9/27/2020 DEROLD HAUFF
CofO Issued 9/27/2020 DEROLD HAUFF
Permit Finaled 9/27/2020 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 10/1/2019 MAX LODER
Miscellaneous Cleared 10/1/2019 MAX LODER
Miscellaneous Cleared 10/1/2019 MAX LODER
ZI Cleared 10/1/2019 MAX LODER
Construction near power lines Cleared 12/18/2019 WALTER RAMIREZ
Address approval Cleared 1/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/24/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/24/2020 ADRIAN CASTRO
Sewer availability Cleared 1/24/2020 ADRIAN CASTRO

Contact Information

Contractor Golden Touch Construction Inc; Lic. No.: 892123-B 461 JESSIE STREET      SAN FERNANDO, CA 91340
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/9/2020 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/23/2020 Partial Approval ROBERT VORHIS
Deputy Drilled-In Anchors 4/3/2020 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/6/2020 Approved JOSEPH MCGARRY
Underground Mechanical 4/30/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/26/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 5/26/2020 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 5/26/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/26/2020 Approved CHRIS CHRISTENSEN
Shower Pan 5/26/2020 Approved CHRIS CHRISTENSEN
Insulation 5/28/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 7/6/2020 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 7/6/2020 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 7/8/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 7/8/2020 Approved ARTHUR SARGSYAN
Green Building Rough 7/8/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 8/27/2020 Approved OSVALDO PARAMO
Final 8/27/2020 Corrections Issued OSVALDO PARAMO
Green Building Final 8/27/2020 Not Ready for Inspection OSVALDO PARAMO
HVAC-Final 8/27/2020 Approved OSVALDO PARAMO
PLUMBING-Final 8/27/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/27/2020 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 8/27/2020 Approved OSVALDO PARAMO
ELECTRICAL-Final 9/14/2020 Approved CHRIS CHRISTENSEN
Final 9/14/2020 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 9/14/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 9/14/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 9/14/2020 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Approved CHRIS CHRISTENSEN